Date: Wed, 12 Jan 2000 12:03:27 +0100 From: George MIKENBERG To: atlas-muon@atlas-lb.cern.ch Subject: Review of 1999 MUON activities Dear colleagues: first let me wish you all a happy and productive year. If one would like to make a balance of the previous year, the keyword would be DELAYS, and not only on the central orders (where most of the timetables have been kept, although with some extra delays due to corrective measurements), but mainly in the preparatory work at the majority of the labs to start the production of the module-0's and subsequent mass production. Indeed, the majority of Module-0's were expected to be now at CERN, for measurements in the tomograph, while the reports made at Eilat show that the corresponding date has moved to June 2000. This is a real delay which if combined with the experienced delay seen by the detectors that moved from Module-0 to production (TGC and RPC, 8 to 6 months) posses serious doubts in our capability to complete our spectrometer on-time. It is clear that during the forthcoming year, and after most of the sites have have acquired enough experience (order of 5 produced chambers), we will need to review the construction schedule (including possible ways to speed up production) and re-evaluate the construction sharing, in order to ensure a minimal working MUON spectrometer at the start of ATLAS. In the meantime, I would like to request from the production sites to send to Gregor and myself a 1/2page monthly report (to be kept confidential) of the progress in each production site. These monthly reports will permit the MUON management to send a more accurate monthly review of activities. It is clear that the success of the project is with the construction sites, independent of any management, and therefore your help and motivation is what it will make this project a success (or a failure). With respect to the most important points that have been achieved during 1999, I would like to mention a few: 1) The RPC passed its chamber and electronics PRR. The Module-0 has been successfully tested. The start of production is, however, delayed by 6 months. 2) TGC production has started, albeit an 8 months delay with respect to the original planning. Final construction speed has been achieved and a total of 160 chambers have been made. 3) The TGC front-end chips have been produced and delivered. The front-end board PRR was successfully pass. 4) The MDT-PRR-1 was successfully pass. The PRR report was very good and the green light was given for the production of Module-0's. 5) A BIS chamber was produced using final production tools and within the expected timetable. Except for a multilayer misalignment due to a construction accident, and whose consequences were predicted, the mechanical characteristics of the chamber, as measured by the tomograph, are within specification. The tube production and testing, with the exception of the gas tightness test, performed well. 6) Most of the Module-0 tubes have been produced at Michigan and Cosenza. The quality control have been implemented, and following the corrections needed in the endplugs design, have achieved the required specifications. 7) Following an heroic set of tests at Seattle, Protvino, Michigan, CERN and Cosenza, the O-ring groove problem of the endplugs design was solved and the design could be finalize. 8) The orders for the tube production, endplugs production and locator were placed at excellent firms, and within the CORE costs. The obtained pre-series are of very good quality. 9) Two acceptable options were qualified for ground contact: laser welding and a new spring solution developed at Protvino. 10) Although after long delays, the automatic wiring machines have been debugged and constructed. 11) After long delays, and serious problems with humidity effects in composite materials, a base-line solution has been accepted for the alignment bars, which consists of monitored metallic bars. Also a procedure has been accepted to come to conclusions on the forward polar alignment sensors. 12) Although with delays, the layout drawing approval has been performed within the MUON community and it will soon start within ATLAS. 13) Major progress has been made in the design and specifications of the small and big wheels, although, the construction and installation of the big wheel might go through a new optimization. The ISTC project that will provide partial funding for the big wheel project has been approved. 14) The preparatory work for the H8 end cap (and maybe also barrel) alignment test facility is beginning to take shape. This will constitute the major full size testing facility of the ATLAS-MUONS. 15) Important progress has been made in having a common LMU-DCS unit that could satisfy aLL THE atlas-muon needs and could provide the possibility of using DCS for initialization purposes. Although the above is an incomplete list, it shows that quite a bit of actions are taking place within the MUON community, however the major action, which is to move into the construction face, still has to take place, and for it to be timely and successful, requires a very strong will from the production sites. Best regards and happy new year George ________________________________________________________________________________ >> This mail has been sent to everyone on the atlas-muon list. >> The list is automatically generated daily from the Atlas members database. >> To change your e-mail address, use "xuserinfo" or "cuserinfo" >> on any CERN central machine. To subscribe/unsubscribe, send a mail to: >> Atlas.Secretariat@cern.ch giving the list name and the action to be taken. ________________________________________________________________________________