|
User Guide for the P61 Pb Ion Beam |
The P0 complex was designed and built to serve the experiments in the high-internsity
underground cavern ECN3 with primary proton and heavy ion beams. The proton beams can be
derived from the T4 or T6 primary targets and serve either the K12 (beam mode P42+K12)
or the H10 branch (beam modes P41 and P61).
Heavy ions are typically only provided to the H10 branch, used for the moment by the NA50 and
NA60 experiments, via the T6 primary target.
In this user guide we describe only the operational aspects of the heavy ion operation of the
P0 complex for NA50 and NA60. The beam mode is thus P61, user index <245>.
1. Preparations at the start of the heavy ion run
At the start of the heavy ion run, a number of operations have to be performed
(by SL-EA)
to allow a correct and safe operation of the P61 beam in heavy ion mode:
- Reconnect the "H10 bends limited" cable to the Chain-9 interlock chain.
This prevents the primary beam from being operational in case the SPS accelerates protons
instead of ions (this interlock must be by-passed during proton operation).
In the rare cases that the SPS wants to go back to protons,
all four TAXES (7, 8, 12 and 13) must be put on small range for the duration of the proton
run
- Make sure that the rectifiers have been cabled for P61 mode, both at the upstream end (T4
-> T6) and at the end of the beam line (P42+K12 ->P61).
- Update the "Planning" to P61 operation.
- Update EABLOK to use P61 (via EA/AREA/INFO/EABLOK/UPDATE).
Check that the Teletext screen shows the correct beam lines and user indices.
- Check that the Ions signal arrives correctly from the PS (via
EA/INT/SAFETY).
- Check that the nodal variable HEAVY is set correctly (e.g. 208 for
Pb82+).
- Put TAX-7 and TAX-8 on small range, TAX-12 and TAX-13 on large range.
- Update the TAXDT file: +145 mm for TAX 7 and 8, -140 mm for TAX 12 and 13.
- The P0 bends should not be limited.
- Disable the DUMP alarm channels 1 and 3 (T10 and TCX water).
- Make sure that the vacuum is closed and that the vacuum is good enough (below 4
10-2 mbar).
- Check the timing distribution in the areas via EA/PIQ/NORTH/STATUS/TIMING/BARRACKS.
- After agreement of the responsible EA beam physicist, remove the manual
veto.
- Prepare and load the correct beam file. For 400 GeV/charge the standard file is P61.1.
- Both TRIGGERS are removed from the beam line.
- Put the T6 target head out (head 0).
- Define the multiplicative factor for NORM-2 to be 0.0122 (=1/82) for Pb82+, to
allow counting in ions rather than charges (via
EA/BEAM/DETECT/SETNORM/GENERAL) and update the threshold accordingly
(TUNE/MEAS/NORM).
- Put the XTGT target OUT via TUNE/SPECIAL/XTGT.
- Load the heavy ion HV settings for the Fiscs.
- Introduce the correct names and pre-scaling factors in the STATUS/GENERAL
programme (via Ctrl-C, then DO 80, DO84, DO99. This needs discussion with the
experiment.
- Use <245>QUICK for TUNE/SPECIAL/QUICK. Update the program if necessary to
select the most relevant scalers and titles (coherent with the previous point).
- Disable P0-survey and NA50-SUR.
- Give control to NA50-2 (index <245>) and 're-install' the NA50 terminal.
Please check that it works correctly and has the correct privileges.
Normally the analog chamber MWPC 1+2 is left in place for the start of the ion period, but
removed immediately after the initial tuning.
As soon as the beam from the SPS onto T6 is stable and correct (check the profiles and
divergence at T6 with EA/BEAM/TARGET/SCAN, respectively EA/BEAM/TARGET/ANGLE),
you are ready to tune the beam.
Sometimes the horizontal spot is much too large (RMS 0.7 mm or larger)
with a flat plateau in the middle. In that case the PCR may be able to improve by re-tuning the
sextupoles for better extraction.
The complete tuning procedure is described separately for the
P61 and H10 sections of the beam.
Please note that the H10 part of the beam offers the choice of 3 different versions of the
optics:
- The so-called Convergent Optics (as for NA10 and NA38)
with magnification 0.25 in the horizontal plane, 0.8 in the vertical plane,
- The so-called Parallel Optics (a wrong
and confusing name!)
with magnification 0.8 in both planes,
- The Intermediate Optics with magnification 0.5
in both planes, i.e. nicely in between the two extremes mentioned above.
The standard optics for heavy ion beams is the Intermediate optics
(sometimes called "Semi-convergent"). It tends to provide the best performance for
physics, but the maximal steering possibilities at the NA50 target are limited to ±3 mm.
For special studies where larger displacements are required (e.g. ZDC calibrations, alignment
studies) the parallel optics is used. This allows displacements of up to a centimetre in each
plane. Fine steering of the end of the beam in parallel optics mode is described in
the H10 User Guide.
2. Observation of the performance of the beam
3. How to find back good conditions?
After a change of beam conditions (re-steering, spill optimisation, RF changes, gradual drifts,
etcetera), it may be necessary to re-optimise the beam somewhat. Normally this can be achieved
in three successive steps:
Find back the beam flux through the first 4 collimators.
Normally Collimators 1 to 4 should have rather small apertures,
centred around zero (typically
of the order of ±3 mm). Leave these apertures unchanged and do the following four scans
(resp. double scans):
If necessary adjust the flux by opening or closing COLL-1 and COLL-3.
In the 2000 run, COLL-2 has some difficulties to set around position 0.
Try to avoid using this collimator!
Never use the SLIT option. Always use the JAWS option.
For small adjustments the program TUNE/SPECIAL/ADJUST-COLL allows to slightly
increase or decrease the gap without making big steps in between (to correct for mechanical
play). Note, however, that this program does not update BIM.0 and that it has no error
trapping. If it does not give the expected result, please use TUNE/SET/COLL instead!
Center the beam at T8.
At the old T8 location, just downstream of Fiscs 5 and 6, the NA60 collaboration has installed
their beamscope detector, size 1x1 mm2. It is important to hit this detector with a
beam that is even smaller (RMS about 0.35 mm in each plane!). This is achieved by the following
"Finger scans":
TUNE/SCAN/FINGER/Fisc #/Position/2/magnet/ etcetera):
|
Fisc Position |
Reference position |
Steering element |
| Fisc-6 (H) | 0.8 | TRIM-10 |
| Fisc-5 (V) | -1.4 | BEND-10 |
Then check with the users that the beam is indeed centred on their detector. If necessary,
fine adjustments should be made.
To correct for the resulting change of angle at T8,
scan BEND-11 through COLL-11 = ±1 mm onto EXPT-1 and set the best value.
Steering to the main experiment
The steering at the experiment is best achieved by Finger scans onto Fiscs 9 and 10:
|
Fisc Position |
Reference position |
Steering element |
| Fisc-10 (H) | -0.2 | BEND-12 |
| Fisc-9 (V) | 1.3 | TRIM-13 |
Please verify and document the beam shape with Fisc profiles of Fiscs 9 and 10 (with
0.2 mm steps).
If necessary, a more precise scan be made onto the halo counter, which has a 3 mm
diameter hole. Normally it is plugged into EXPT-10.
Before the scans, the experiment should remove their target,
otherwise the halo rate would be dominated by backsplash from the target.
In both planes it is preferred to
perform double scans: BEND12 + 3.7 TRIM12
for the horizontal,
TRIM13 + 2.12 TRIM11 for the vertical position.
In both cases it is recommended to take ±5 steps of 4 Amps. E.g.:
TUNE / SCAN / EXPT / 10 / 2 / BEND / 12 / TRIM / 12 / 5 / 4 / 3.7
Select the values corresponding to the center of the hole.
After this operation it is important to check that the flux and halo rates are correct again.
Sometimes the experiment wants to scan the trigger rate (EXPT-4) versus X and Y position over a
wider range. The trigger rate increases dramatically when the beam hits the edges of the
Beryllium Oxyde absorber (diameter 7 mm). For this the range of the double scans is
insufficient and single scans of BEND-12 and TRIM-13 onto EXPT-4 (range ±60 Amps for
BEND-12, ±80 Amps for TRIM13).
Last updated : 10 October 2000 by
Lau Gatignon