Linac 2 Start Up 2011


BE Department

Mode Switching Procedure

eLogbook

2009 Start-up

 

Friday 04/02/2011 AM DSO tests on Linac2 and PS
Friday 04/02/2011 PM First beam to the Linac2 dump.
RF Setting up.
No SISWatchdog, survey beam manually.
Monday 07/02/2011 AM Beam to the Linac2 dump.
Continue RF Setting up.
No SISWatchdog, survey beam manually.
Monday 07/02/2011 PM [Condition] Beam stable to dump.
Start SISWatchdog testing.
Test recovery of SISWatchdog to front end reboots.
Tuesday 08/02/2011 AM Interlock chassis tests - Do interlocks cut the beam.
Interlock chasis readout tests.

Tuesday 08/02/2011 PM If SISWatchdog not passed tests, 2nd round of tests.
[Decision] SISWatchdog ok. If not, return to GMWatchdog, test the GMWatchdog.

Wednesday 09/02/2011 AM [Condition] A working watchdog, PS tunnel ok for beam.
Beam to LBE and LBS measurement lines. Test watchdog, interlocks. Measure beam in these lines.
Wednesday 09/02/2011 PM Reserve 1/2 day.
Aim beam to PSB at end of the day.

Richard Scrivens AB-ABP-HSL