Friday 04/02/2011 AM | DSO tests on Linac2 and PS |
Friday 04/02/2011 PM |
First beam to the Linac2 dump. RF Setting up. No SISWatchdog, survey beam manually. |
Monday 07/02/2011 AM |
Beam to the Linac2 dump. Continue RF Setting up. No SISWatchdog, survey beam manually. |
Monday 07/02/2011 PM |
[Condition] Beam stable to dump. Start SISWatchdog testing. Test recovery of SISWatchdog to front end reboots. |
Tuesday 08/02/2011 AM |
Interlock chassis tests - Do interlocks cut the beam. Interlock chasis readout tests. |
Tuesday 08/02/2011 PM |
If SISWatchdog not passed tests, 2nd round of tests. [Decision] SISWatchdog ok. If not, return to GMWatchdog, test the GMWatchdog. |
Wednesday 09/02/2011 AM |
[Condition] A working watchdog, PS tunnel ok for beam. Beam to LBE and LBS measurement lines. Test watchdog, interlocks. Measure beam in these lines. |
Wednesday 09/02/2011 PM |
Reserve 1/2 day. Aim beam to PSB at end of the day. |
Richard Scrivens AB-ABP-HSL