DSF Development Wiki Page
please feel free to add all information about all of the DSF developments for the Alice SPD
DSF News
For all of the colaboration please feel free to ad news data here
-
Petra - 12 Apr 2006:
Telephone installed inside the ALICE area in the cleanroom. Phone number: 76953
-
Petra - 12 Apr 2006:
Cabling work of sector 0 and sector 1 still ongoing. Work foreseen to be finished by the end of this week (week 15).
-
Petra - 30 Mar 2006:
prepared rack for LV-HV power supplies. Remaining cables for sector 1 and replacement cables for sector 0 will be installed in the next 2-3 days.
-
Petra - 29 Mar 2006:
Installation of the optical bench completed. 1400 kg granite table moved into the cleanroom. See pictures in Picture Gallery!
-
Petra - 23 Feb 2006:
TOTAL POWER CUT in DSF on March 7 (8:00) till March 8 (13:00) due to work on the power connections for the CMS cleanroom.
-
Petra - 06 Feb 2006
LV cable installation for sector 1 finished
-
Main.ctorcato - 03 Feb 2006
Laying optical cables to sector 1
-
Main.ctorcato - 03 Feb 2006
Hey! now we have a
wiki lets start adding information
DSF General Information