DJRA1.4.1 - Infrastructure Area Work Plan and Status Report

Due Date

03 July 2010

JRA1-internal

  • see https://twiki.cern.ch/twiki/bin/view/EMI/EMIJRA1T5DJRA141
  • This deliverable contains the detailed work plan of the Infrastructure Services technical area compliant with the overall EMI Technical Development Plan. The plan is released early in the project life and updated every year including a status report on the achievements of the past 12 months compared to the planned objectives. The status report at M03 will cover the state-of-the art while the work plan at M36 will provide recommendations for further work.
  • DJRA1.4.1 Draft v. 0.1 (DOC)(ODT)
  • DJRA1.4.1 Final Version for PEB by Laurence, see Final version send to PEB (2010-07-12)
  • 2010-07-28 - Morris: Deliverable is rejected from JRA1 leadership due to less internal discussions within the infrastructure area and the document itself (see review available on the status page)

Review tracking

  • 05/10/10 - M. Riedel informs PO draft 3 ready for review DOC
  • 14/10/10 - v3 sent to F. Giacomini (SA1) , B. Hagemeier (JRA1), PEB for review; deadline 22/10
  • 15/10/10 - B. Hagemeier sent review
  • 19/10/10 - B. Konya sent review
  • 25/10/10 - F. Giacomini sent review
  • All reviews received; updated DJRA141 expected 02/11/10
  • 01/11/10 - L. Field produced v7
  • 03/11/10 - L. Field feedback on reviewers' comments added in twiki
  • Reviewers feedback on v7 expected 15/11/10
  • 10/11/10 - v7 accepted by B. Hagemeier
  • 10/11/10 - v7 accepted by B. Konya with additional comments, see TD review page
  • 21/11/10 - v7 accepted by F. Giacomini with additional comments, see SA1 review page
  • 25/11/10 - L. Field produced v8 with the following changes 1) Changed of target dates to synchronize with the EMI 1.0 schedule. 2) Removal of a two objectives for the ARC Information system as they should be not be in the first year plan. 3) Added an objective for the EMI registry. The outstanding issues with the reviewers are issues where we disagree and I am happy to defend my position.
  • Pending SA1 acceptance of v8; deadline 01/12
  • 29/11/10 - None of the SA1 open issues were addressed in v8; noted in SA1 review wiki
  • 03/11/10 - PEB decision to accept v8 as final despite unaddressed SA1 issues
  • PO to creation final version, upload in CDS and submit to the EC.
  • 08/12/10 - L. Field has updated SA1 review wiki with further explanations on unaddressed SA1 issues.
  • 13/12/2010 - Final pdf uploaded in CDS and submitted to the EC

Reviewers

Edit | Attach | Watch | Print version | History: r27 < r26 < r25 < r24 < r23 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r27 - 2011-02-25 - unknown
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    EMI All webs login

This site is powered by the TWiki collaboration platform Powered by PerlCopyright &© 2008-2024 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
or Ideas, requests, problems regarding TWiki? use Discourse or Send feedback