IT/ST Co-ordination Meeting
regarding Bat.513.
Meeting held
1/2/2000
Present: ST: A.Funken
IT: T.Cass, D.J.Underhill, T.Smith, M.Vergari, R.Minchin.
T Cass reminded those present that the object of the
meeting was to ensure that for both short term and long term issues, we were
able to
- agree on the issues,
- ensure things were not forgotten, and
- decide how to progress on each issue.
As the extension to Bat 186 was being covered in
parallel discussions it was agreed to limit our discussion to issues concerning
Bat 513.
The issues to be addressed concern Space, Power, Air
Conditioning, Access and Safety. These can be viewed as follows:
SPACE:
- Short term: "Ensure we can accommodate the LHC testbed
facility (or facilities), that will be introduced progressively from autumn
2000".
- Long term: "Make available a total "raised floor" area
of 2,000 m2 for LHC era computing farms".
Comments: DJU commented that care was needed in some of the
short term choices as they could have longer repercussions.
Tim Smith should supply us with the space requirements for the
test bed facility. ACTION: TS.
Tony
reminded us that the 2,000 m2 required for LHC did not include space for home
directory servers or for network infrastructure.
DJU and RPM had looked for space that could be recuperated within
B513. They had located
- ~500m2 in the barn - recuperating all except the
offices along the west wall and moving the corridor alongside them.
- ~1100 m2 in the basement - progressively recuperating
space as equipment is moved out - e.g. STK robots as soon as their new
location is made available and emptying of the 3480 archives, all of which
should be able to be thrown away by 2003.
- ~200 m2 in the old MG room. Due to the noise level in
this room it might be more suited to a replacement archive.
- ~200 m2 in the storage area between the MG room and
the corridor to the tape vault.
Almost all
of the above space would require the relocation of people or equipment or both.
For instance, alternative office space should be found before considering moving
people from the barn. Part of the 1st floor could be considered.
It was agreed that here is sufficient space within the
Computer Room for our requirements until mid 2001, including the test bed
facility.
Tim will provide a graph of the space
requirements envisaged for the next 6 years. ACTION: TS.
It would not seem necessary to build another floor or building to
house computing equipment provided that the designated areas can be
liberated.
Tony suggests that we investigate
pre-equipping the tape vault with false floor and power by mid 2001.
POWER:
- Short term: "Ensure a backup power supply can take
over within 10 minutes of any failure of the primary EDF/EOS supply."
- Long term: "Ensure electricity supply is adequate for
the foreseen load of 2 Megawatts in 2005. This includes distribution, backup
and emergency power off issues".
Comments: At a recent ST division workshop in Chamonix it
was proposed that the automation for switching over to an emergency power supply
would be renewed.
The three diesel generators
currently used have a maximum deliverable output of 2.1 Mw. They have to supply
power to Point 1 and all of the Meyrin site, including the Computer
Center, and therefore would not be able to supply the 2Mw the computer centre
will require.
The power consumption in B513 is
extremely difficult to subdivide due to the interconnectedness of the systems.
This makes it virtually impossible to consider powering off selected machines in
an attempt to reduce the demand.
DJU commented
that there is also a 2Mw limit on Substation 23 which supplies the Computer
Centre.
AIR CONDITIONING:
- Short term: Seems ok.
- Long term: "Ensure that the air conditioning
arrangements are both adequate for the installed equipment foreseen in 2005
and compatible with any fire detection and extinction equipment."
Comments: The airconditioning system
currently installed is only used to about 30% of its capacity. However, what is
not understood is whether it could cope with the heat dissipated by equipment
using 2Mw of electricity. This needs to be checked.
ACCESS CONTROL:
- Short term: Move to the CERN standard access control
system.
- Long term: Any issues?
Comments: One question is whether the new system should
control the whole building or just the computer room. There is a large
difference in price. Covering the whole building has implications on the use of
the large metal doors used for deliveries. ST proposes that the two large blue
metal doors on the Saleve side of the building be replaced by roller doors. IT
is awaiting an offer.
DJU should find out who
pays for maintenance once the system is installed. ACTION: DJU.
Tony enquired if the CERN access system, which was
installed to cope with the LEP era, would need to be upgraded before LHC.
SAFETY:
- Short term: "Work with TIS to document the
improvements/modifications to B513 that are required, desirable or suggested
for the safety of personnel, data and equipment IN THAT ORDER"
- Long term: "Ensure that all required
improvements/modifications are implemented and as many as feasible from the
desirable or suggested lists"
Comments: In meetings with ST and TIS it has been suggested
that the outdated smoke detection systems in the offices and barn be
replaced.
The very sensitive laser smoke detector
in the roof is a single unit. To provide increased safety, this should be
duplicated.
It is not obvious if use of the
sprinkler system in the vault is advisable, given the nature of the equipment
installed there.
DJU will circulate reports that
discussed replacing the wall between the computer room and the barn with
something more resistant to fire. ACTION: DJU. This idea is largely
negated by the centralised air condition system which circulates air throughout
the whole building.
The high ceiling of the
computer room provides considerable space for heat dissipation but makes it
difficult to trace the origin of any smoke.
OTHER BUSINESS:
TC and AF will investigate possible sites to visit or
companies that might provide consultancy (e.g. BT or IBM).
NEXT MEETING: 15th Feb at 10:00. Meet at the coffee machine and
visit the building. Follow up meeting 29 th Feb. 31-1/002.
Richard
Minchin.