B513 Planning Meeting, 27th August 2001

Present:          Tony Cass, Anne Funken, Jukka Lindroos, Dick Minchin, Bruno Pichler, David Underhill, Mario Vergari, Tim Whibley

1.             Vault conversion planning

·         The DLT robot (Timberwolf) has to be moved by STK engineers; it is assumed that this will be done after the 3 new silos are installed in B613.

·         The wall around S-406 is scheduled to be demolished, but a part of the equipment here is required for the UPS and battery room. Jukka will investigate ways to provide temporary air conditioning to these areas.

·         Anne will provide a cost estimate for removing the old electrical distribution equipment.

a.       S-413/vault: suppress or (preferred) leave as access to new technical area

b.      S-415/S-030 leave or (preferred) suppress. A clarification on the “fire exit” status of this door is required.

c.       The height of the new emergency exit to be created between the vault and S-030 needs to be decided. For this, the height of the false floor must be agreed.

·         Anne said that the detailed timings for the LV supply work would only be known after a discussion with the contractor (which will take place in the next couple of weeks).It is not expected that this work will delay the completion of the vault conversion but it was noted that this work will be competing with other work across CERN during the accelerator shutdown period..

2.             AOB