B513 Planning Meeting, 13th September 2001

Present:          Nigel Baddams, Tony Cass, Anne Funken, Jukka Lindroos, Dick Minchin, David Underhill, Mario Vergari, Tim Whibley

1.             Previous Minutes & Matters Arising

·         Temporary airconditioning for UPS and batteries. The UPS has a dedicated air conditioning unit which can almost certainly be used for the battery room as well. One unit has to remain operational in S-406, but this will not present an obstacle to the civil engineering work.

·         Cost for removal of old electrical distribution equipment. This has still to be finalised, but Anne gave an initial estimate of around 4KCHF for removal of the switchboard and the associated normabarres. However, Tony pointed out that there are many electrical cables running in cable trays to supply power sockets mounted on the pillars. These (and the old-style normabarres on the ceiling) should also be removed.

·         Tony has still to organise discussions about the civil engineering work with Bernard Louchet and the contractor.

2.             Long Term Arrangments for Electrical Supply to B513

3.             AOB