B513 Planning Meeting, 9th November 2001
Present:
Nigel Baddams, Tony Cass, Marc Collignon, Anne Funken, Dick
Minchin, Bruno Pichler, Mario Vergari
1.
Previous Minutes
- We still
await a quote for the removal of the newer HVAC unit. [Finally received on
November 21st: CHF4,860, including all associated equipment.]
- The cost
for removing the additional electrical supply equipment amounts to 16KCHF.
Tony felt this was unreasonable expensive given that we had been quoted
6KCHF for removing the switchboard and “ground level” distribution. Anne
explained that the 16KCHF covered the removal of all the old lighting
installation, not just the ceiling mounted normabarres. It was agreed that
the exact details of the quote should be checked.
- The
different possibilities form remote PDU control will be discussed at an ST
meeting next week. The basic arrangement is to have a unit in each PDU to
control each outgoing feeder and make measurements. To allow remote
control from the TCR or the operators box, the control units in each PDU
have to be connected to a single PLC in the substation. A PVSS interface
could be considered later. The cost would be 10KCHF for the PLC in the
substation plus 1KCHF per PDU for the control unit.
- Anne asked if there was any intention to connect the two
power inputs provided on the STK silos to the different UPS level power
sources. This is not planned as the silos are for physics use. However, we
could consider connecting using two different normabarres.
- It will not be possible to test the inrush current for a rack
of PCs before December as all systems are in production. However, further
“steady state” measures can be made.
- Tony has still to discuss the need for pre-heating coils
within IT division.
- Orders for fibres and associated equipment will be issued
soon; Marc still needs to determine the exact lengths needed, including
for the fibres between the vault and the computer centre as the routing is
not yet decided. Here, Tony suggested it might be best to take the cables
vertically into the barn and then across to the network area rather than
across at the basement level and then up.
- Tony has had some preliminary discussions on reserving
one area of the vault for silos, but further work is needed. Overall, the
idea is not bad, but there are difficulties if we cannot have identical
configurations in B513 and B613.
2.
Order Status and Work Planning
- The technical specs for the civil engineering work have
been prepared but have yet to be reviewed. Anne does not think that this
work can begin before end-January; further, Charles Scalisi will not be
back at CERN to supervise the work before February.
- The “heavy work”, demolition and construction of walls,
should take around one month. On this basis, Tony’s planning suggests that
the vault conversion will not be complete until early June 2002, rather
than mid-April. It was noted that the details of the various separating
walls in the former MG room depend on the size of the smoke extraction
system, and so cannot be known before air conditioning tender is in.
However, the vault conversion does not depend on this work.
- The HVAC tender should leave CERN in the week of
November26th with a closing date in mid-January. After the
order is placed towards the end of January, the company will need two
weeks to study the system in detail before ordering the various
components. Delivery of the air conditioning units themselves would take
around 6 weeks so these will not be here before the end of March.
- The delivery delays for the HVAC units should not be
problematic given the civil engineering days, but this is not absolutely
clear. Anne will be preparing a formal ST project plan to check these
issues.
·
The tender/order for the false floor will now be
separate from that for the heavy construction work. Further investigations into
the fixing arrangements for false floor feet show that
a.
constructors guarantee the quality of fixation whether or not
glue or bolts are used, and
b.
the difference in the type of feet that are used means that a
bolted structure costs three times more than a glued structure.
Given this last point, we should not insist on
bolted feet. Tony commented that the fixation mechanism is less important now
that we are pre-installing light cables rather than dragging around heavy IBM
channel cables.
·
Whatever the fixation mechanism, we have to take into
account the floor rails for the old tape racks. Dick pointed out that these
rails are prouder of floor in some areas as the floor slopes.
- Based on experience from B613, Nigel and Anne believe
that the false floor installation should be done after the PDU and HVAC
unit installation, but before normabarre and cable tray installation.
- Painting and cleaning (of the walls as well as the floor)
need to be coordinated with the various installation tasks. These tasks
should be costed and ordered now such that they can be done by the
existing contract.
- Dick Minchin pointed out that we should make sure the
floor is cleaned properly and that some form of shot-blasting will
probably be needed to clean off various patches of glue and other residues
of past work. This shot-blasting needs to be costed; the 2KCHF cost
mentioned for the archive store was for an area one-sixth the size and the
work was carried out a good few years ago.
3.
Floor Plan Review
- Nigel showed a first coordination plan for the vault.
Network information has still to be included; Marc will send the necessary
information. At popular request the next plan will be on a 1:50 scale.
- Anne and Jukka have agreed the needs for perforated
tiles. The air conditioning requires 10% of floor area to be space.
Perforated tiles are 40% space and thus 25% of the tiles must be
perforated to achieve the 10% figure. These tiles cannot support a
permanent equipment load, but there is no problem wheeling equipment
across the tiles during, e.g., installation.
- The false
floor order will specify the requirement for 25% of perforated tiles. The
exact placement will have to be agreed. For this to be done, the rack
placement needs to be included on the coordination plan.
4.
B513 Substation
- Anne and Nigel presented a very preliminary plan of a
future substation housed in a bunker under the main car park.
- The preliminary plan houses the 200kW UPS in the bunker.
This is unlikely to be necessary as this UPS (and associated batteries,
even for 2 hour cover) can be accommodated in the existing low voltage
switchgear area.
- Without the 200kW UPS, the bunker would be ~18m wide and
extend ~9m out from B513. Although some size reduction could be achieved,
this is probably not necessary as the bunker would fit on the Saleve side of
the Barn door.
- The major construction problem is likely to be dealing
with the air conditioning ducts that lead to vents on this side of the
building. It is likely that the bunker will have to be pushed out further
from the building to accommodate these ducts. However, there is sufficient
space between the ducts to install doors with the height required for
access.
- Anne has established that the existing transformers can be
installed outside, although shelters will be required. These shelters
would cost 4KCHF each, but this is substantially less than the cost of two
new transformers.
- Anne and Nigel will be refining the substation and bunker
plans over the next couple of weeks.
5.
AOB
- There was
some discussion of Emergency Stop requirements. It would be desirable to
have independent Local Emergency Stops for both the vault and the machine
room, but these can’t be installed now without much work that would become
unnecessary with the new substation. It was noted that, in any case, both
zones would still be affected by the general building emergency stop, for
which many buttons are distributed across B513. The need for these buttons
will be clarified with Guy Salomon.
- Anne has
been discussing lightening protection with Raymond Cambarrat. Apparently
the building has a lightning protection (paratonnere) system, but there is
no information about this or if it is in a good condition or not. Also, if
this does exist, then parafoudre equipment is required at the substation
level. Anne would like to commission a study required to check on the
current system and make recommendations. Tony agreed that this could go
ahead, but asked that the study should give an indication of the level of
risk—in terms of both frequency of occurrence and likely consequences.
- Marc will
take care of the dismantling of the old structured cabling network.
- Next meeting: 14:00 on Friday 23rd November.