B513 Planning Meeting, 23rd November

Present:          Nigel Baddams, Tony Cass, Marc Collignon, Anne Funken, Jukka Lindroos, Dick Minchin, Dave Underhill, Mario Vergari, Tim Whibley

1.             Previous Minutes

·         Various quotes for renewal of the lighting in the vault have been received.

a.       CHF3,700 for the installation of lighting under the false floor.

b.      CHF4,400 for the installation of emergency evacuation lights, including CHF2,000 for a placement study (which also covers false floor lighting).

c.       CHF28K, including CHF3k for a study, to cover the replacement of 130 ceiling lights, 90% on standard power, 10% supplied by the UPS.

The price for the ceiling lights was considered a little expensive, although one reason for the cost could be that the ceiling is relatively high. Anne will check within ST to see if some of this cost could be counted as general maintenance work—the new light fittings would reduce the ongoing cost of tube replacement.

·         Coordination plan.

a.       Nigel has network information, but this has yet to be added.

b.      There will be separate ceiling and floor plans.

c.       Plans should include drainage for hvac units. How is the gradient of these drains ensured? Jukka had thought of attaching them to the false floor, but all other equipment has an independent support structure.

d.      Question: can we fit 8 (or 6) robots in the vault? The preference is to have each robot connected to two others; the minimum requirement is that there be at least two paths to each robot.

2.             Floor plans

3.             Overall Planning

·         Anne has prepared an overall plan for the work. The key considerations when ordering the work were

a.       Everything should be cleaned and painted before major installation work starts. The cleaning/painting to start at the ceiling and work down to the floor.

b.      The support structure for hvac units will be installed before the false floor.

c.       False floor tiles to be put on only after cables are in place

4.             B513 Substation and Bunker

5.             AOB