B513 Planning Meeting, 27th June 2002
Present:
Tony Cass, Anne Funken, Jukka Lindroos
1.
Previous Minutes
- The previous minutes were updated with various corrections from
Anne.
2.
Planning for the new Substation
- Sizing of the bunker depends on
- the required battery
lifetime for the 200kW UPS solution.
To a large extent, the useful lifetime depends on how quickly the vault
would overheat in the absence of air-conditioning. For a full load of
100kW, the temperature would rise to 40°C in 40 minutes. For the moment, Tony still prefers to assume a
2 hour requirement for this UPS.
- The space required for
the 2MW UPS—which depends in turn on the air conditioning requirements.
The heat load for the MGE solution is
confirmed at 200kW. Anne commented that ST Microelectronics have reserved
an area of 40m ´ 100m for 6 MGE UPS units. This is not felt to be necessary,
but the existing UPS area is not sufficient. Although all 11 units will
fit, the size of the room is such that a maximum of 5 can be cooled—and
this requires the installation of a dedicated hvac unit in the room.
- Jukka will consider options for adding cooling capacity to the
current UPS area. If possible, we should make use of capacity in the
general hvac system as this allows free cooling in winter. However, an
extra duct would have to be installed. Account must also be taken of the
hvac needs of the telephone exchange and batteries, both of which are
covered by the hvac unit that cools the UPS today. [Anne also noted that
the desire to use the existing hvac system could conflict with the need to
run the UPS air conditioning from the UPS itself—see point 2.8.]
- Unfortunately, we still have no information on the heat load
for Gutor systems. This should be available by the end of July but in the
meanwhile the design office will prepare a bunker layout assuming the use
of MGE UPS systems. Two versions will be prepared, one assuming the use of
2MVA transformers (the preferred solution), the other for 3MVA
transformers.
- Despite the general contract with Gutor for UPS systems, a
tender could be required for our UPS systems or could be useful to obtain
the best price for the large systems. If bunker construction is to start
in 2002 then the bunker layout must assume a worst case for UPS
requirements. Unless the Gutor space/hvac requirements are greater than
for the MGE solution, therefore, the layout prepared during July will be
sent to the external design consultancy.
- Assuming construction begins at the end of 2002, the new
substation should be in operation for January/February 2004. It was noted
that the switchover implies an interruption for any equipment connected to
the existing PDUs. As the PDUs in the vault have two inputs, equipment in the
vault will be unaffected. (Equally, any equipment connected to any new
PDUs installed in the machine room would also be unaffected.)
- The power needs of the UPS and air conditioning systems were
also discussed. During any power failure, the hvac units must be powered
from the 2MW UPS, but this load is estimated at 20kW, thus there is little
interference with the physics load. Finally, although larger than
expected, the power loads of the UPS and associated systems are still
believed to fit within the available capacity.
3.
Upgrading the existing machine
room
- If all goes according to schedule, the equipment in the “right
hand side” (from in front of the operator area to the barn wall) of the
machine room will have been moved to the vault or removed by June 2003. We
should therefore start to plan for the upgrade of the electrical
distribution in this area.
4.
AOB
- Dave and Anne are to agree the initial location of the Magelis
screen. The cable should be long enough to reach any part of the operators
console and also to reach into the barn.
- Next meeting: 25th July, 14:00