CERN home pageInformation Technology division Welcome

Machine Room Installation and Safety Planning

The highlights of the Machine Room Installation and Safety Planning work are listed below. Minutes of the various planning meetings are also available.
June 2000 A first campaign to remove unnecessary rubbish and packaging material from the machine room is completed. [Unfortunately, rubbish and packaging creeps back during the summer...]
May 2000 Safety Linkmen agree that IT should follow the recommendations of sections 8.1, 8.2 and 8.10 from BS6266. These include prohibiting eating, drinking and smoking in the machine room.
April 2000 Divisional Management approves principal of Safety Linkmen for groups with large amount of equipment in B513.

 Tony Cass, 28th August, 2000