B513 Planning Meeting, 25th July 2002
Present:
Tony Cass, Anne Funken, Jose Miranda-Vizuete, Dave Underhill
1.
Previous Minutes
- The previous minutes were updated with various corrections from
Anne.
2.
Substation
- Gutor have still not provided any information about the heat
load of their UPS equipment. Anne has given them a deadline of July 31st
to provide this.
- Similarly, Anne still needs further input on the hvac loads and
the type of power required (normal, assured, secure). This is being
followed up with ST/CV.
- The electrical plan will be prepared by Anne by the end of
August. From this Nigel will prepare plans to be sent to the bureau
d’etude. Preparation of the final design documents can be expected to take
until the end of October.
- Unfortunately, a review of the project has suggested that a tender
might be necessary for the civil engineering work. Fortunately, we can use
an existing market survey but, if this is the case, the tender cannot be
sent out until the design documents have been finalised, so early November
at the earliest. A start date in 2002 would thus be ruled out. Work could
perhaps start in February and continue until July.
- A switchover date in early 2004 (before the PS startup) is
still desirable—i.e. before any significant addition of equipment. The switchover
must be done without any major interruption, although a power cut of 4-6
hours would be acceptable given that this would not affect equipment
installed in the vault.
- Anne asked again about any phasing of UPS capacity. Tony considered
that assuming the load today is 800kW, UPS capacity could be phased as
- 1.2MW by end 2004,
- 1.6MW by end 2006 and
- 2MW by end 2007.
- However, Tony emphasised that the upgrade work is being
financed by Phase 1 of the LCG project and so no funding is available
after 2005.
In principle, ST should provide a contribution in respect of equipment
that would normally need to be replaced before LHC startup. The extent of
this contribution remains to be assessed, but may not be more than the
costs for two low voltage switchboards (around 150KCHF).
- There was some discussion about whether or not to announce a tender
for UPS equipment at the September FC. We do not yet know if this is
needed, but delaying the announcement until December means the adjudication
could not be before the September 2003 Finance Committee, leaving little
time for installation before the 2004 PS startup. Anne will discuss this
within ST/EL.
- All other required equipment is covered by contracts, apart
from the air conditioning. The estimated cost for the air conditioning
equipment, though, is below 200kCHF so no tender is required, just a price
enquiry.
- After the last meeting, Jukka provided an estimate of the rate
of temperature rise for 100kW of equipment in the machine room and the
vault without air conditioning. In the machine room, it would take almost
2 hours (110 minutes) for the temperature to reach 40C, but this level
would be reached in the vault within 40 minutes. However, as the air
conditioning units in the vault are rated at 80kW, powering just one unit
from the critical load UPS would maintain the tempreature within
acceptable levels even for a 2 hour lifetime of the UPS batteries. The
extra load on 1 unit should be acceptable, but this arrangement would
require a change to the current design as no provision has been made to
power any units from a UPS.
3.
Machine Room Upgrade
- The basic requirement for the electrical distribution system in
the machine room is that this should not be the limiting factor for
machine installation. The available power density should therefore be at
least 1.5kW/m2
(the level of the air conditioning capacity) spread evenly across the room.
Assuming a 2m wide technical zone around the walls, the usable area is
approximately 1200m2, and so the total power available would be 1.8MW. Provision
should be made for a further 200kW to be supplied to the Barn, but final
planning for this area should await clarification of the nature of the
load (e.g. PC equipment or a control room).
- IT has no particular constraints on the layout of the normabarres.
It is clearly sensible, though, to reuse as much of the existing system as
possible so the majority of the normabarres would be aligned parallel to
the barn wall. IT will have to take account of this when installing
equipment in order to ensure that all services are aligned with the power
distribution.
- Installation should start in the area in front of the operators
box from mid-2003. No problems are foreseen with this timetable as all
equipment is covered by existing contracts. Anne should define the precise
PDUs to be replaced in this first stage so that IT can ensure that all the
affected systems are moved to the vault.
4.
AOB
- Next meeting: 14:00 on Thursday 8th August.