Quarterly plan for August-October 2012
Job monitoring area
Historical view
ATLAS
Implementation of feature requests and bug fixes tracked through Savannah.
CMS
-
Interactive interface
CMS
-
Task monitoring
ATLAS
- Production task monitoring. Implementation feature requests submitted by ATLAS community. Tracked through Savannah (September-October)
- Analysis task monitoring, validation of implementation from the point of view of security (end of August)
- Analysis task monitoring, start implementation of the resubmission capability from the UI. requires discussion with Panda developers (end of October)
DDM accounting
Input from Eddie is needed
Transfer monitoring area
ATLAS DDM Dashboard
Input from David is required
WLCG Transfers Dashboard
- Implementation of transfer latency monitoring for the FTS transfers. First prototype is ready for validation by the ATLAS and CMS community by the end of August.
- First prototype including xrootd transfers deployed on the test server (August)
- Work with people running xrootd federation in order to enable data flow from all servers (August-October). Currently data collected at CERN is not complete
- Collect and discuss requirements for federation level monitoring (August-October)
- Installation of the hadoop cluster at CERN for federation-level monitoring (August-September)
- Creating RPM of the xrootd collector capable of processing data reported with UDP with further publishing to ActiveMQ (August-September)
- Creating collector for ALICE consuming data from the ML repository and republishing it to ActiveMQ (September-October)
Google Earth
-
Handling of the Dashboard cluster
-
Pablo, please , draft a plan here
-
SUM
Validation of SUM after SAM migration to versio 17
Detailed input from team members
--
JuliaAndreeva - 20-Aug-2012