February 2008 |
Sunday |
Monday |
Tuesday |
Wednesday |
Thursday |
Friday |
Saturday |
|
|
|
|
|
01 |
02 |
03 |
04 Mover commissioning at RAL |
05 Mover commissioning at RAL |
06 Mover commissioning at RAL |
07 Mover commissioning at RAL |
08 Mover commissioning at RAL |
09 Travel to KEK |
10 Travel to KEK |
11 Vacation (National Founding Day) |
12 Installation Luis travels to KEK |
13 Installation Luis arrives Measure surface of sample foils with interferometer at KEK prior to installation |
14 Installation Mark arrives |
15 Installation |
16 James arrives |
17 |
18 testing readout of beamline instrumentation |
19 testing readout of beamline instrumentation |
20 testing readout of beamline instrumentation Nige arrives |
21 Two shifts |
22 Half shift, 1300-1700. Sample #1 removed and sample #2 inserted after shift ends. Pump down over weekend. |
23 |
24 |
25 |
26 Measure sample # 1 with Keyence VK8510 interferometer (c/o Watanabe-san in Mech. Workshop) Day shift: sample #2 study |
27 a.m.: George and Nige leave |
28 Day shift: requested time *iff no other group needs it |
29 Day shift: sample #2 continues. After 1700, Dismount from beamline, radiation test equipment. If cool, then pack for shipping, remove from beam hall, otherwise leave in hall for activity retesting on 3 Mar. |
|