2012 Resource Installation Status (version: 5 Mar 2012)

Tier-1 CPU Disk Tape Tier-2
CERN 85% in April and 100% at the end of May 85% in April and 100% at the end of May ok -
Canada, TRIUMF In production In production by 1 Apr In production by 1 Apr Tier-2 east federation: ok. Tier-2 west federation: CPU: ok, disk: expected on time (in procurement).
France, CC-IN2P3 97% in production (no further increase for 2012) 88% in production (no further increase for 2012) 98% of pledge will be provided Lyon Tier-2: CPU: 99 %, Disk: 97% (no further increase for 2012). GRIF Tier-2: 10 % reduction of ATLAS pledges. IPHC Tier-2: ok for Apr. SUBATECH Tier-2: disk may be delayed due to late delivery. CPPM Tier-2: by 1 Apr. LPSC Tier-2: CPU: by Apr, disk: 90% by end Apr. LAPP Tier-2: disk may be affected by supply problems. LPC Tier-2: disk by Sep.
Germany, GridKA by end Jun (with additional kHEPSPECs - compensation for late delivery) by early Apr ok Aachen CMS-Tier2: ok. Atlas-T2s MPPMU, Wuppertal: ok, LRZ and Freiburg ready before April 1st. GoeGrid (Goettingen): Disk delayed. Alice-T2 @ GSI: CPUs in place, Disks may be delayed by a few weeks. DESY(Atlas, CMS, LHCb) ok.
Italy, CNAF ~80% now and rest in production by Apr ~30% now and rest in production by end Apr by end Apr Alice T2s: CPU: by Apr, disk: mostly ok (complete by end Jun). Atlas T2s: CPU: by Apr, disk: by end Apr. CMS T2s: CPU: by Apr, disk: 50% by Apr (rest by Sep). LHCb T2: CPU: by Apr, no disk.
Netherlands, NIKHEF/SARA Expected for Oct (in negotiation) Expected for Oct (in negotiation) ok no tier-2s
Nordic Data Grid Facility (NDGF) Installed 100% by ~Jun (80% installed or in shipping and rest expected in Apr) ok SE-SNIC-T2: ok. HIP-FI-T2: disk is being intalled. SIGMA-UNINETT-T2: by ~Jun (delivery in Apr).
Spain, PIC By mid-March (35% above pledge) By mid-March (35% above pledge) ok ATLAS T2 Federation Spain: CPU: ok (15% above pledge), disk: by 1 Apr (85% now). CMS T2 Federation Spain: CPU: ok (25% above pledge), disk: ok (10% above pledge). LHCb T2 Federation Spain: ok. ATLAS LIP T2 Federation, Portugal: ok.
Tapei, ASGC Installed 90% in March and 100% by July ok T2 TW-FTT: CPU:ok. Disk: 72.5% in March and 100% by July. CMS T2 LCG_KNU: ok
UK, RAL deployment by Apr deployment by Apr ok UK Tier 2s: All ok
USA, BNL Installed Installed ok US-ATLAS: CPU: ok. Disk: 88% and rest in Apr
USA, FNAL Installed Installed ok 7 US Tier 2 sites: CPU: ok. Disk: ok (aggregate of 7 PB, with some site-to-site variation above and below 1 PB). SPRACE T2: by end of May (pledge: 10 kHS06 and 720 TB of disk).
- - - - Greece IOANNINA T2 CPU: 62% installed, remainder by September, Disk: 94% installed, no further increase expected as only 30% used.
- - - - Israel Tier2 CPU: 100% available, new CPUs to be installed by mid-May, Disk: 66% installed, full pledge expected by mid-May.
- - - - India Kolkata Tier-2 CPU: 100% available, Disk: 96% installed, full pledge expected by (tbc).
- - - - KISTI ALICE Tier-2 CPU: 100% available, Disk: 100% available.
- - - - CH-CHIPP-CSCS Tier-2 CPU: 83% available by April and at least 100% end July following re-location of the T2 site, Disk: 100% available.
- - - - T2-IN-TIFR CPU: 82% available, 100% end July, Disk: 77% available, 100% end July.
- - - - Turkey, Turkish Tier-2 Federation CPU: 45% available, Disk: 56% available, due to reorganisation definitive date for full pledge not yet known.
- - - - T2_HU_Budapest CPU: ok, Disk: ok.
- - - - Czech Republic FZU Prague CPU: ok, Disk:80% Available, 100% from July.
- - - - JP-TOKYO-ATLAS-T2 CPU: ok, 133%, Disk: ok.
- - - - Austrian Tier-2 Federation CPU: ok, Disk: ok.
- - - - Estonia NICPB CPU: ok, Disk: ok. Preliminary estimate from current tender process is to double the computing capacity and increase the storage capacity to 1PB while improving the overall performance. Availability estimated at late summer/early Autumn
- - - - WLCG-PK-CMS-T2 CPU: ok, Disk: 56% installed, 100% June-July.
- - - - RO-LCG Tier-2 CPU: ok revised, increased pledge, Disk: 90% installed, 100% August following procurement delays revised, increased pledge.
- - - - Ukranian Tier-2 Federation CPU: 50% available, 100% expected by September, Disk: 50% available, 100% expected by September.
- - - - Australia Tier-2 CPU: 77% available, 100% expected by May, Disk: 70% available, 100% expected by May.
- - - - Slovenia SiGNET Tier-2 CPU: 133% available, Disk: 66% available, delay due to funding delays and cooling upgrade in the computing room which is also delayed 100% expected by Autumn.
- - - - WLCG-CN-IHEP CPU: 92% available, 100% expected by mid-June, Disk: 100%.
Edit | Attach | Watch | Print version | History: r27 < r26 < r25 < r24 < r23 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r27 - 2012-04-10 - SueFoffano
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    LCG All webs login

This site is powered by the TWiki collaboration platform Powered by PerlCopyright &© 2008-2024 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
or Ideas, requests, problems regarding TWiki? use Discourse or Send feedback