-- JamieShiers - 12 Feb 2006

Timetable for 2006

January SC3 disk repeat – NominalRates capped at 150MB/s/ SRM 2.1 delivered (?) July Tape throughput tests at full nominal rates!
February CHEP w/s – T1-T1 Use Cases, SC3 disk – tape repeat (50MB/s, 5 drives) August T2 Milestones – debugging of tape results if needed
March Detailed plan for SC4 service agreed (M/W + DM service enhancements). gLite 3.0 release beta testing September LHCC review – rerun of tape tests if required?
April SC4 disk – disk (nominal) and disk – tape (reduced) throughput tests. gLite 3.0 release available for distribution October WLCG Service Officially opened. Capacity continues to build up.
May Installation, configuration and testing of gLite 3.0 release at sites. November 1st WLCG ‘conference’. All sites have network / tape h/w in production(?)
June Start of SC4 productionTests by experiments of ‘T1 Use Cases’. ‘Tier2 workshop’ – identification of key Use Cases and Milestones for T2s December ‘Final’ service / middleware review leading to early 2007 upgrades for LHC data taking??
Edit | Attach | Watch | Print version | History: r4 < r3 < r2 < r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r4 - 2006-03-07 - HarryRenshall
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    LCG All webs login

This site is powered by the TWiki collaboration platform Powered by PerlCopyright &© 2008-2024 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
or Ideas, requests, problems regarding TWiki? use Discourse or Send feedback