Tier-1 Tier-2 Transfers Plan for INFN
Modified on: 2007-02-19
Date: Wed, 25 Jan 2006 15:16:26 +0100
From: Luca dell'Agnello, Tiziana Ferrari
* Tier-2s
Currently only a list of candidate Tier-2 sites is available:
BARI ALICE, CMS
CATANIA ALICE
LNF ATLAS
LNL ALICE, CMS
MILANO ATLAS
NAPOLI ATLAS
PISA CMS
ROMA1 ATLAS, CMS
TORINO ALICE
CNAF LHCb
The LHCb Tier-2 at CNAF will be colocated with the Tier-1.
* SRM
** December 2005: 60% of sites have working SRM interface
** End of March 2006: All sites (including Tier-1) will be able to
transfer files using FTS and SRM 2.1
** March - April 2006: Test of interoperability between Tier-1 and Tier-2s
* FTS
** December 2005: FTS client configured for 60% sites
** December 2005: 60% of Tier-1 <--> Tier-2 channels configured
** End of January 2006: Evaluation of requirements for an Intra-Tier-2
FTS channel infrastructure
** End of February 2006: All Tier-2 sites have FTS client configured
** End of March 2006: Implementation and testing of Intra-Tier-2 FTS
channel infrastructure completed (Use case to be verified)
* Tier-1 - Tier-1 transfers
** End of January 2006: Definition of intra Tier-1 transfer requirements
** End of February 2006: Implementation of dedicated path to FZK Tier-1
* Tier-1 - Tier-2s transfers
** Second half of March 2006: peak rate tests Tier-1 to Tier-2s
** Seconf half of March 2006: short (~ 2 days) individual sustained tests to all Tier-2s
** First half of April 2006: sustained transfer tests Tier-1 to all Tier-2s (target rates according to the table below)
** Second half of April 2006: aggregate Tier-2 to Tier-1 transfers at target rate as specified in the table below
Tier-2 exp IN rate (Mb/s) OUT rate (Mb/s)
-----------------------------------------------------------------------
BARI ALICE, CMS 320 120
CATANIA ALICE 120 15
LNF ATLAS 120 15
LNL ALICE, CMS 320 120
MILANO ATLAS 120 15
NAPOLI ATLAS 120 15
PISA CMS 220 120
ROMA1 ATLAS, CMS 320 120
TORINO ALICE 120 15
* Tier-2 - Tier-2 Transfers (Use case to be understood)
** Second half of April: for each experiment, peak rate tests for every Tier-2 to a given other Tier-2 of choice
** Second half of April: sustained transfer (for every Tier-2) at target rate (as in table above) in parallel with sustained transfer from Tier-1 to that given Tier-2 (in order to verify the concurrency of read/write operations)
* LFC
** End of February 2006: LFC installed at each Tier-2
* VO Boxes
** Vo boxes currently installed at Tier-1 but subject to results of the review (January 2006)
** Installation in Tier-2s TBD