GEM Foil Leakage Current

%COMPLETE1%

Special thanks to Jeremie Merlin for writing the indepth guide for this experiment, available LINK GOES HERE.

Introduction

Discussion from Jeremie's document to go here.

Theory

Discussion & images from Jeremie's document go here.

Measurement & Procedure

If you have ordered a 10cm-by-10cm GEM chamber kit from CERN there will be three GEM foils and one drift foil inside of a protective case. This case should only be opened inside a clean room of class <= 10,000. It is important to know the difference between the GEM and the drift foils.

The GEM foils are slightly transparent and have two electrodes, one each for the top and bottom of the foil, external to the frame. The GEM foils are also coated with copper on both sides giving a "mirror" finish to the foil as shown below:

GEM_Foil.JPG GEM_Foil_Reverse_Side.JPG

on the other hand, the drift foil is coated with copper on only one side; and has only one electrode external to the frame:

Drift_Foil.JPG Drift_Foil_Reverse_Side.JPG

Do not unseal the protective case until you are inside a clean room.

Initial Setup

The leakage current measurements should only be performed in a clean room of class <= 10,000. The temperature, ambient pressure, and humidity of the room should be monitored as these can have an impact on the results of the leakage current test. The procedure below illustrates the steps to test one foil at a time; parallization of this process is implied.

  1. Remove the GEM foil from their protective case.
  2. Place the GEM foil on its support structure:
  3. GEM_Foil_On_Support.JPG

  4. Place the GEM foil and support structure inside the plexiglass box. Affix connections to GEM foil electrodes.
  5. Check the connectivity to the foil from outside the plexiglas box by measuring the capacitance of the foils. For a good quality (read "clean enough to continue") 10cm-by-10cm foil this value should be ~5.6nF as shown below:
  6. GEM_Foil_ConnectionCheck.JPG

  7. Flush the plexiglass box with nitrogen gas (flow rate > 50 mL/hr). Monitor the temperature, pressure, and humidity inside the box. The humidity inside the plexiglas box should be well below the humidity outside the box.
  8. Connect the bananna cable end of the SHV cable to the GEM foil. Connect the other end of the SHV cable to channel A, located on the back of the module, of the HV power supply on the right of the image below.

    High_Voltage_Power_Supply.JPG

You are now ready for the "One Minute Test."

One Minute Leagakge Current Test

This test should only be performed on GEM foils which have a capacitance of ~5.6nF.

Please click through the 14 steps below before starting the test. GEM foils can be easily damaged by high currents or excessive localized discharges. If a high sustained current (> 1 nA) is observed for longer than 60 seconds or if consecutive discharges (sparks) occur in the same position immediately remove the applied voltage from the foil.

One_Minute_Test_HV_Step1.png
One_Minute_Test_HV_Step2.png
One_Minute_Test_HV_Step3.png
One_Minute_Test_HV_Step4.png
One_Minute_Test_HV_Step5.png
One_Minute_Test_HV_Step6.png
One_Minute_Test_HV_Step7.png
One_Minute_Test_HV_Step8.png
One_Minute_Test_HV_Step9.png
One_Minute_Test_HV_Step10.png
One_Minute_Test_HV_Step11.png
One_Minute_Test_HV_Step12.png
One_Minute_Test_HV_Step13.png
One_Minute_Test_HV_Step14.png

A foil that passes the "One Minute" test can move to the Automatic Measurement described in the next subsection.

Automatic Measurement of the Leagakge Current Test

This test should only be performed on GEM foils which have passed the "One Minute" test.

This test consists of measuring the leakage current by applying a series of alternating voltages to the GEM foil and monitoring its stability throughout this procedure. An automated test protocol has been developed using LabVIEW.

  1. Connect the bananna cable end of hte SHV cable to the GEM foil if it is not already connected. Connect the other end of SHV cable to channel 0, located on the back of the module, of the programmable power supply on the left of the image below:
  2. High_Voltage_Power_Supply.JPG

  3. Enable the HV for channel 0 of the CAEN N1471A HV programmable power supply by moving the kill switch up (shown below) if it is not already enabled.

    Automatic_Measurement_Test_HV.png

  4. Connect both the USB cables from the Keithley multimeter and the CAEN N1471A HV programmable power cable to the computer if they are not already connected.
  5. Open "Device Manager" to check for proper communication. If the computer recognizes both devices a "National Instruments GPIB Interfaces" field will appear in the main list and a new USB entry will appear under "Ports (COM & LPT), as shown below:
  6. Device_Manager_WithPowerSupply.PNG

  7. Note the port of the CAEN N1471A HV programmable power supply. In the example above it is "COM10," although it may be assigned a different number in your setup.
  8. Open the "LeakageTest-N1471A-KILL.vi" shortcut on the desktop if it is not already open.
  9. Navigate to the "Configuration" tab. Change the "Set Data Folder" location to a pre-existing filepath. Then start the LabVIEW virtual interface (VI). These steps are shown graphically:
  10. Automatic_Measurement_LabVIEW_Step1.png

  11. Fill out the "User Name" and "Foil ID" fields in the pop up menu then press "OK" as shown below. Note the "Foil ID" must be unique . A subdirectory inside the "Set Data Folder" filepath will be created with the name of the "Foil ID" field.

    Automatic_Measurement_LabVIEW_Step2.png

  12. Ensure the "VISA resource name in" drop down menu has the CAEN N1471A Module's com port (identified above) selected then press the "Start Test" button. Graphical reference shown below:
  13. Automatic_Measurement_LabVIEW_Step3.png

  14. The program will switch to the "Leakage Current Test" tab and display a pop-up window. Click "OK" without changing any values. Graphical reference shown below:
  15. Automatic_Measurement_LabVIEW_Step4.png

  16. Navigate to the "Vmon and Imon Monitoring" tabs as shown in the image below. If you do not observe the voltage to begin ramping up immediately in the highlighted Vmon graphs double check that the HV on the CAEN N1471A HV programmable power supply is enabled. If this is enabled restart the LabVIEW program and repeat steps X - Y until you see the voltage ramping.
  17. Automatic_Measurement_LabVIEW_Step5.png

  18. Once you observe the voltage begin to ramp you may observe some discharges on the foils. An example of a discharge is shown in the image below:
  19. Automatic_Measurement_LabVIEW_Step6.png

  20. The procedure will terminate when either a) the maximum number of allowed discharges has been reached, or b) the test procedure has reached the final step. An example of what the monitoring graphs should look at the end of the automated procedure is shown below:
  21. LabVIEW_LeakageCurrent_Completed.PNG

Repeat this procedure until three GEM foils have been identified with leakage currents below 1nA and a sufficiently low number of discharges occurring. Once this occurs you are ready to move onto detector assembly.

-- BrianDorney - 26 May 2014

Topic attachments
I Attachment History Action Size Date Who Comment
PNGpng Automatic_Measurement_LabVIEW_Step1.png r1 manage 543.2 K 2014-05-19 - 22:08 BrianDorney  
PNGpng Automatic_Measurement_LabVIEW_Step2.png r1 manage 439.4 K 2014-05-19 - 22:08 BrianDorney  
PNGpng Automatic_Measurement_LabVIEW_Step3.png r1 manage 476.4 K 2014-05-19 - 22:08 BrianDorney  
PNGpng Automatic_Measurement_LabVIEW_Step4.png r1 manage 438.2 K 2014-05-19 - 22:08 BrianDorney  
PNGpng Automatic_Measurement_LabVIEW_Step5.png r1 manage 627.5 K 2014-05-19 - 22:08 BrianDorney  
PNGpng Automatic_Measurement_LabVIEW_Step6.png r1 manage 686.0 K 2014-05-19 - 22:08 BrianDorney  
PNGpng Automatic_Measurement_Test_HV.png r1 manage 333.7 K 2014-05-19 - 22:22 BrianDorney  
PNGpng Device_Manager_WithPowerSupply.PNG r1 manage 110.3 K 2014-05-19 - 21:27 BrianDorney  
JPEGjpg Drift_Foil.JPG r1 manage 6181.2 K 2014-05-19 - 19:32 BrianDorney  
JPEGjpg Drift_Foil_Reverse_Side.JPG r1 manage 5066.8 K 2014-05-19 - 19:32 BrianDorney  
JPEGjpg GEM_Foil.JPG r1 manage 5685.2 K 2014-05-19 - 19:32 BrianDorney  
JPEGjpg GEM_Foil_ConnectionCheck.JPG r1 manage 5645.7 K 2014-05-19 - 20:12 BrianDorney  
JPEGjpg GEM_Foil_On_Support.JPG r1 manage 5218.6 K 2014-05-19 - 19:59 BrianDorney  
JPEGjpg GEM_Foil_Reverse_Side.JPG r1 manage 5164.8 K 2014-05-19 - 19:32 BrianDorney  
JPEGjpg High_Voltage_Power_Supply.JPG r1 manage 6942.3 K 2014-05-19 - 19:59 BrianDorney  
PNGpng LabVIEW_LeakageCurrent_Completed.PNG r1 manage 212.0 K 2014-05-19 - 22:43 BrianDorney  
PNGpng One_Minute_Test_HV_Step1.png r1 manage 317.1 K 2014-05-19 - 18:47 BrianDorney  
PNGpng One_Minute_Test_HV_Step10.png r1 manage 320.0 K 2014-05-19 - 18:47 BrianDorney  
PNGpng One_Minute_Test_HV_Step11.png r1 manage 323.0 K 2014-05-19 - 18:48 BrianDorney  
PNGpng One_Minute_Test_HV_Step12.png r1 manage 316.2 K 2014-05-26 - 10:21 BrianDorney  
PNGpng One_Minute_Test_HV_Step13.png r1 manage 325.5 K 2014-05-19 - 18:48 BrianDorney  
PNGpng One_Minute_Test_HV_Step14.png r1 manage 316.7 K 2014-05-19 - 18:48 BrianDorney  
PNGpng One_Minute_Test_HV_Step2.png r1 manage 322.5 K 2014-05-19 - 18:47 BrianDorney  
PNGpng One_Minute_Test_HV_Step3.png r1 manage 323.4 K 2014-05-19 - 18:47 BrianDorney  
PNGpng One_Minute_Test_HV_Step4.png r1 manage 323.9 K 2014-05-19 - 18:47 BrianDorney  
PNGpng One_Minute_Test_HV_Step5.png r1 manage 322.5 K 2014-05-19 - 18:47 BrianDorney  
PNGpng One_Minute_Test_HV_Step6.png r1 manage 323.4 K 2014-05-19 - 18:47 BrianDorney  
PNGpng One_Minute_Test_HV_Step7.png r1 manage 323.3 K 2014-05-26 - 10:21 BrianDorney  
PNGpng One_Minute_Test_HV_Step8.png r1 manage 323.7 K 2014-05-19 - 18:47 BrianDorney  
PNGpng One_Minute_Test_HV_Step9.png r1 manage 323.7 K 2014-05-19 - 18:47 BrianDorney  
Edit | Attach | Watch | Print version | History: r7 < r6 < r5 < r4 < r3 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r7 - 2014-09-21 - PatriziaBarria
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    MPGD All webs login

This site is powered by the TWiki collaboration platform Powered by PerlCopyright &© 2008-2024 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
or Ideas, requests, problems regarding TWiki? use Discourse or Send feedback