ATLAS Muon Management
General Issues
|
|
Chamber Construction Issues
Modified 27 Nov 2002 by Steven Goldfarb
-
Cracks in brass gas tubelets
- change to stainless steel whenever possible
- check chambers already made, using epoxy
- evaluate overall costs
- look into treating some brass tubes
-
Service integration in the chambers
- use H8 to perform first integration test
-
Gluing of alignment platform
- Need to understand what went wrong, how to improve procedure
-
Positioning of alignment platforms
- need procedure to calibrate or cross-check
Chamber Completion Issues
Modified 27 Nov 2002 by Steven Goldfarb
-
Known difficulties in some of the groups
- Lack of funding for Greek institutes (~1MCHF)
- Lack of funding for additional manpower to complete RPC chambers on time
- Lack of funding for Chinese institutes (~500kUSD)
- Slow production rate of large TGC chambers at Weizmann
|