ATLAS Detector Commissioning using Offline Software

Table of Contents

  1. Introduction
  2. Contact persons
  3. Meetings
  4. Mailing List
  5. Documents
  6. See also

1. Introduction

Commissioning brings the ATLAS systems (detectors, TDAQ, HLT) from just installed to operational. It refers mainly to activities at Point 1 and to integration. Offline commissioning deals primarily with the use of offline software during detector commissioning.

Commissioning proceeds in four phases:

  1. Subsystem standalone commissioning
    • DCS: LV, HV, cooling, gas, safety, DB recording and retrieving
    • DAQ: pedestal runs, electronic calibration, write and analyze data
  2. Integrate systems into full detector
  3. Cosmic rays
    • Record data, analyze/understand, distribute data to remote sites
  4. Single beam data, first collisions
    • Similar to cosmic rays, but working with increasingly higher rates.

Offline commissioning tackles the requirements for the ATLAS offline software during all four commissioning phases. The phases will overlap since different systems may be in different phases. Commissioning has started and will last well into 2007.

2. Contact persons

Detector / system Contact person
Inner Detector Maria Costa, Michael Hauschild
Liquid Argon Calorimeter Hong Ma, Remi Lafaye, Manuella Vincter
Tile Calorimeter Sasha Solodkov, Jose Maneira
Muon Spectrometer Claude Guyot, Rosy Nikolaidou
Databases Richard Hawkings, Torre Wenaus
TDAQ Guiseppe Mornacchi, Livio Mapelli
HLT Cristobal Padilla
Physics Maarten Boonekamp
Simulation Adele Rimoldi, Andrea Di Simone
Convenors of offline commissioning Rob McPherson,
Hans von der Schmitt

3. Meetings

All commissioning meetings (including offline commissioning) are on the CERN agenda maker.

Meeting Date Main topics of meeting
Offline commissioning 26 January 2005 Feedback on initial questionnaire on detector needs
DAQ infrastructure for computing
Database plans
Offline commissioning 22 March 2005 Cosmic triggers
Detector plans for Phase 3
Offline commissioning 26 April 2005 Conditions DB and Distributed Data Management
New event format
Monitoring environment
Offline commissioning
(SW week - Summary talk)
25 May 2005 Event displays
Cosmics simulation including timing
Detector feedback
Offline commissioning 12 July 2005 COOL update
Detector feedback
Offline commissioning
(SW week - Summary talk)
28 September 2005 DB/DM update
Monitoring
Detector plans/requests
Offline commissioning 14 November 2005 SW installation at pit
DDM with commissioning data
AthenaMonitoring environment
Updates from detectors
Commissioning data workshop 27 January 2006 Data storage and distribution
From Testbeam to Commissioning
Metadata for commissioning and beyond
Offline commissioning
(SW week - Summary talk)
4 April 2006 Update on monitoring
Trigger simulation for commissioning
Updates on DDM and SW installation at Point1
Detector status, plans, data rates and volumes
Commissioning data bookkeeping

See also: Meetings of the Technical Management Board TMB

4. Mailing List

5. Documents

6. See also

Inner Detector Database Project Offline Computing
Liquid Argon Calorimeter Trigger, DAQ and DCS Physics
Tile Calorimeter
Muon Spectrometer Monitoring Working Group Installation

↑ Top