Design
|
|
Layout
Installation
|
|
|
Cryostat Cross Section
|
|
|
Coil Cross Section
|
|
|
Schematic
Bird's Eye View
|
|
|
Coil Support
|
|
Conductor and Winding
|
|
Conductor Joint
|
|
|
Test Winding
|
|
|
Superconductor
|
|
Coil
|
|
Coil Completed
|
|
|
Coil Front View
with Al-strips
|
|
|
Side View
on Inner Warm Vessel
|
|
|
Ready for Shipment
|
|
|
Arrived at CERN
September 2001
|
|
Proximity Cryogenics
|
|
Valve Unit
|
|
|
Control Dewar
|
|
Electric Circuit
|
|
Electric Diagram
|
|
Factory Test at Toshiba, Japan
|
|
Layout
|
|
|
Test Cryostat
|
|
|
Proximity Cryogenics
|
|
|
Reached 8400A
26 December 2000
|
|
|
Test Results
|
|
Integration into Barrel Cryostat and On-surface Test in Bldg.180 at CERN
|
|
Layout
|
|
|
May 2002
|
|
|
August 2003
|
|
|
February 2004
|
|
|
June 2004
|
|
|
Chimney Joint
25 May 2002
|
|
|
Chimney Joint
30 May 2002
|
|
|
Survey
October 2003
|
|
|
Coil Joint
23 February 2004
|
|
|
Coil Insertion
26 February 2004
|
|
|
Coil Insertion
26 Feb. 2004
|
|
|
Bulkhead Assembly
|
|
|
Reached 8136A
5 July 2004
|
|
|
Test Team
|
|
Installation in the ATLAS Detector
|
|
Transport to
Point 1
October 2004
|
|
|
Descent from SX1
October 2004
|
|
|
Descent into UX15
October 2004
|
|
|
Survey
January 2005
|
|
|
Move into the Barrel Toroid
November 2005
|
|
|
In Position
8 November 2005
|
|
|
Bulkhead Joint
30 November 2005
|
|
|
Bulkhead Joint
1 December 2005
|
|
|
Control Dewar Installation
14 December 2005
|
|
|
Control Dewar Joint
18 January 2006
|
|
Functional Test and Commissioning
|
|
Cool Down
17 - 23 May 2006
|
|
|
1 kA
MCS Display
24 May 2006
|
|
|
1 kA
PWC Display
24 May 2006
|
|
|
8 kA
Full Field
1 August 2006
|
|
|
Full Field!
1 August 2006
|
|