+ = in progress
|
X = finished
|
|
Central Solenoid
|
April - July 1999
|
Coil Winding
|
May 2000
|
Factory Test of Chimney and Control Dewar
|
26 December 2000
|
Factory Test of the Coil
(reached 8400 A)
|
June 2001
|
Factory Test of Extension-Chimney
|
3 September 2001
|
Arrival at CERN
|
26 February 2004
|
Cryostat Integration
|
5 July 2004
|
On-surface Test reaches 8200 A
|
28 October 2004
|
Descent into Cavern
|
4 November 2005
|
Barrel and Solenoid moved into detector
|
6 March 2006
|
Vacuum pumping started of Barrel Cryostat
|
12 April 2006
|
Cooling liquid argon calorimeter started
|
17 May 2006
|
Cooling solenoid started
|
23 May 2006
|
Cold, superconducting and
reached 1 kA
|
1 August 2006
|
Reached full field:
2 tesla
|
|