Civil Engineering Work 19th February - 5th April 2002

Vault HVAC room

19th - 27th February
Walls are demolished, hvac equipment removed and concrete supports demolished. Note the interesting use of tape shelving units in the 3rd picture!
20020219_1.jpg (166964 bytes)20020220_1.jpg (169993 bytes)20020220_4.jpg (167147 bytes)20020226_2.jpg (163003 bytes)20020227_1.jpg (157416 bytes)
13th - 22nd March
The duct feeding the hvac unit with fresh air is demolished (this will be routed under the false floor in future) and the walls of the new room are built up.
20020313_1.jpg (163035 bytes)20020315_5.jpg (171902 bytes)20020315_6.jpg (166445 bytes)20020319_4.jpg (166351 bytes)20020322_2.jpg (177644 bytes)

MG Room HVAC room

20th February - 1st March
The supporting walls and the dalle holorib are demolished. Initially, this was done by ramming the walls and watching the dalle fall! Safer methods were introduced later...
The "holorib" sheeting which supported the concrete sheeting can be seen in the 4th picture.
The final picture shows a view through into the former CS storage area; a new wall will be built here in line with the rest of the back wall.
20020220_3.jpg (163998 bytes)20020221_1.jpg (160516 bytes)20020226_4.jpg (166234 bytes)20020226_3.jpg (157978 bytes)20020301_1.jpg (165889 bytes)20020301_2.jpg (160038 bytes)
6th - 19th March
Building up the walls between the vault and the storage areas.
20020306_2.jpg (165328 bytes)20020307_1.jpg (160688 bytes)20020313_2.jpg (166926 bytes)20020315_3.jpg (162151 bytes)20020319_3.jpg (165634 bytes)

UPS battery room

20th February - 22nd March
The door into the vault is blocked off and the cloison covering the brick wall is replaced—evidently this wall was built from the inside of the battery area.
20020220_7.jpg (156322 bytes)20020306_3.jpg (164873 bytes)20020319_5.jpg (163248 bytes)20020322_1.jpg (160348 bytes)

Turning the old MG room into new storage space

26th February
The left hand picture shows the inside wall of the MG room with the grilles for air to come from the plenum. This wall is knocked down (pictures 2 & 3) as the plenum is no longer needed.
The door into the hvac plant room (picture 2) will be bricked up. Picture 4 shows a new wall being built up here (and the left edge shows some of the new cloisons.)
The last two pictures show work to break openings into the Saleve side corridor; the final picture shows clearly the blocking up of the former doors into the MG room.
20020226_1.jpg (168071 bytes)20020306_6.jpg (169359 bytes)20020315_1.jpg (173505 bytes)20020319_1.jpg (158925 bytes)20020327_1.jpg (160773 bytes)20020327_2.jpg (149853 bytes)

Small items

Filling in the grooves from the old tape rack rails.
20020227_2.jpg (156942 bytes)20020315_4.jpg (158166 bytes)20020319_2.jpg (164325 bytes)
Cutting a hole so the smoke extraction duct can connect to the chimney.  
20020402_2.jpg (157174 bytes)20020405_1.jpg (161908 bytes)

An empty vault ready for the installation work

5th April
20020405_3.jpg (173486 bytes)
 