Vault Conversion

Equipping the vault as a Machine Room

Preparatory work, 5th April - 27th May

Not much visible happens in April and May due to the various holidays, but new lighting is installed in the vault and in the new storage areas.
The first two pictures are from 24th April. The first shows some of the original cable trays; the second shows the network cables neatly attached to the ceiling. The next two pictures show a brighter vault with the new view from the blue doors.
20020424_1.jpg (157332 bytes)20020424_3.jpg (169233 bytes)20020524_4.jpg (151816 bytes)20020523_8.jpg (157901 bytes)
The duct for the UPS battery room is now in its proper place.
20020524_2.jpg (170247 bytes)20020527_3.jpg (150587 bytes)
The big power supply for the air conditioning unit has been removed (big patch on the far wall in the left picture) and replaced by this small box to the right of the unit in the second picture.
20020527_4.jpg (162282 bytes)20020523_4.jpg (150911 bytes)
Smoke curtains are installed. These descend 50cm from the ceiling and are designed to stop smoke spreading at ceiling level.
20020523_5.jpg (160468 bytes)20020524_3.jpg (157038 bytes)

Painting the floor and installing cable trays, 23rd May - 14th June

The floor is sanded down (dusty!) and painted; the walls are painted to a height of 70cm, the depth of the false floor.
20020523_1.jpg (155327 bytes)20020523_5.jpg (160468 bytes)20020527_2.jpg (154800 bytes)20020603_2.jpg (153780 bytes)20020603_3.jpg (158292 bytes)20020603_4.jpg (153441 bytes)
Cable trays are installed around the edge of the room for electrical and control cables and across the room for network cables (fibre & utp)
20020614_2.jpg (151183 bytes)20020614_7.jpg (155639 bytes)20020614_8.jpg (156908 bytes)

Installing the new air conditioning, 14th June -

Piping to carry cold water to the air conditioning units is run around the outside of the room under the false floor. (As originally planned; at one intermediate stage it had been thought that this piping would be at ceiling level.)
The units will sit on frames as shown in the 4th picture. The water flow to each unit will be controlled by special valves. Each has a serial number and is carefully calibrated so the flow rate is known for a given dial setting.
20020621_3.jpg (157214 bytes)20020621_4.jpg (164455 bytes)20020621_6.jpg (159179 bytes)20020628_2.jpg (147101 bytes)20020628_1.jpg (161867 bytes)
Waste water piping is installed—and means the network cable trays have to be rerouted over the water pipes.
20020705_3.jpg (159970 bytes)20020705_4.jpg (161371 bytes)20020705_7.jpg (152725 bytes)
Foamglass insulation and protection is added...
20020726_3.jpg (169628 bytes)20020726_2.jpg (157813 bytes)
The new underfloor duct for the UPS battery room hvac unit is installed. This will also provide fresh air to one of the vault units.
20020726_1.jpg (157660 bytes)20020823_10.jpg (153048 bytes)
This chimney above the archive store needs to be replaced by a fan for smoke extraction.
20020604_1.jpg (150306 bytes)20020725_2.jpg (171714 bytes)20020726_9.jpg (174161 bytes)20020726_7.jpg (180078 bytes)20020812_04.jpg (347617 bytes)20020812_02.jpg (410415 bytes)20020812_03.jpg (364590 bytes)20020812_05.jpg (382520 bytes)20020812_06.jpg (493403 bytes)20020812_07.jpg (473635 bytes)20020812_08.jpg (485822 bytes)
Should it ever be necessary(!), smoke will be extracted from each zone into a duct passing through the storage areas and then back into the machine room to connect to the chimney and the extraction fan.
20020819_4.jpg (176161 bytes)20020819_3.jpg (147772 bytes)20020821_8.jpg (151380 bytes)20020821_2.jpg (154119 bytes)20020821_3.jpg (152474 bytes)
20020821_4.jpg (155187 bytes)20020823_08.jpg (156355 bytes)20020823_09.jpg (147279 bytes)20020905_6.jpg (155218 bytes)20020912_5.jpg (152526 bytes)20020912_4.jpg (156029 bytes)
20020905_7.jpg (150389 bytes)20020905_3.jpg (154209 bytes)20020912_6.jpg (147690 bytes)
20020905_5.jpg (154961 bytes)20020912_1.jpg (158021 bytes)20020912_3.jpg (138658 bytes)
 

Electrical Distribution Work, 5th July -

The PDUs arrive; their bases are installed and cables are pulled.
20020705_10.jpg (164068 bytes)20020628_3.jpg (148954 bytes)20020712_5.jpg (159426 bytes)
The PDUs and cables are positioned (the 3rd picture shows cables laid out to supply the normabarres).
Boxes for the 48V supply and controls are installed.
20020719_1.jpg (159182 bytes)20020719_2.jpg (157739 bytes)20020719_3.jpg (151516 bytes)20020719_5.jpg (152794 bytes)
The normabarres are installed as are cable trays for IT. (The first photograph shows the set of trays under the future robot area.)
20020719_7.jpg (158837 bytes)20020726_5.jpg (163172 bytes)20020726_2.jpg (157813 bytes)
The forest of normabarres is in place and most are connected to the PDUs.
20020802_02.jpg (164095 bytes)20020802_03.jpg (160854 bytes)20020802_04.jpg (164427 bytes)20020802_05.jpg (162348 bytes)
A wired up PDU sitting neatly level with the false floor...
20020823_05.jpg (157598 bytes)
 
 
 
 

Network installation

Fibre then UTP cables are installed and the cables left waiting for the equipment racks.
20020712_3.jpg (160496 bytes)20020712_4.jpg (168808 bytes)20020719_4.jpg (158764 bytes)20020719_1.jpg (159182 bytes)20020719_6.jpg (163277 bytes)

Installing the false floor, 19th August - 13th September

19th August: everything arrives and the first panels are laid out.
20020819_1.jpg (155968 bytes)20020819_2.jpg (155965 bytes)
21st August: 8 rows in place. Things look very different from 70cm up!
20020821_1.jpg (156389 bytes)20020821_6.jpg (158425 bytes)20020821_7.jpg (156807 bytes)
23rd August: 12 rows in place.
The careful planning pays off---everything fits neatly together under the floor.
20020823_01.jpg (157560 bytes)20020823_03.jpg (159676 bytes)20020823_06.jpg (165800 bytes)20020823_02.jpg (162373 bytes)
28th August
20020828_1.jpg (152527 bytes)20020828_2.jpg (160114 bytes)20020828_3.jpg (157394 bytes)20020828_4.jpg (171793 bytes)
30th August
20020830_1.jpg (161468 bytes)20020830_2.jpg (157136 bytes)20020830_4.jpg (171734 bytes)20020830_3.jpg (153827 bytes)
5th September
20020905_1.jpg (158773 bytes)20020905_2.jpg (162780 bytes)20020905_4.jpg (158257 bytes)20020905_5.jpg (154961 bytes)
12th September
20020912_1.jpg (158021 bytes)20020912_2.jpg (158343 bytes)
 
 

The new vault is ready for IT equipment!

5th April
 
 