JRA1.1 - Process System: Reporting Top 5 Key Development Highlights to PEB
Goal
The purpose of establishing this system is to setup a process that reports the top 5 key development highlights to the Project Executive Board (
PEB) and the Project Director on a regular basis.
Process
A short system view aout the process is as follows:
- Data area leader: Sends e-mail to JRA1 WP leader (every 2nd Friday)
- Compute area leader: Sends e-mail to JRA1 WP leader (every 2nd Friday)
- Security area leader: Puts development highlights into the following Wiki page and keep it updated: JRA1 Security Development Highlights (update at least every 2nd Friday)
- Infrastructure area leader: Sends e-mail to JRA1 WP leader (every 2nd Friday)
Quick Reference
- Quick Reference: Reporting Top 5 Key Development Highlights to PEB:
Process Tracking
- 2010-08-02 - Morris: Process system send around for review
- 2010-08-02 - Patrick: Process itself approved (although having issues)
- 2010-08-10 - Morris and Laurence: Discussion of the process w.r.t. infrastructure area
- 2010-08-16 - Morris: Update of Process (infrastructure area) and process start