This page lists the project Milestones as defined in the project DoW (Description of Work). The list includes themes and contact details of the authors, the milestone expected and actual achievement date and the current status. A link to the milestone reports in the official EMI Document Repository is also provided as soon as the milestones are officially achievement.

The EMI milestone review procedure is available here.

Status Number Title WP number Lead Beneficiary Task Number Task Leader Author Due Date Achievement Date Notes
Yes / Done MS1 MNA1.1 - Project Kick-Off Meeting 1-NA1 1-CERN NA1.1 Alberto Di Meglio Florida Estrella 1(May-10) May-10  
Yes / Done MS10 MNA2.1 - Project web presence 2-NA2 10-INFN NA2.2 Pina Salente Pina Salente 1(May-10) May-10  
Yes / Done MS17 MSA1.1 - EMI Support Units integrated in GGUS 3-SA1 8-JUELICH SA1.5 Mathilde Romberg Mathilde Romberg 1(May-10) Oct-10  
Yes / Done MS2 MNA1.2 - Project management information system and tools 1-NA1 1-CERN NA1.1 Alberto Di Meglio Alberto Di Meglio 1(May-10) May-10  
Yes / Done MS22 MSA2.1 - Software development tools and software repositories in place 4-SA2 1-CERN SA2.4 Lorenzo Dini Lorenzo Dini 1(May-10) May-10  
Yes / Done MS26 MJRA1.1 - Security Workshop 5-JRA1 18-UH JRA1.4 John White John White 2(Jun-10) May-10  
Yes / Done MS11 MNA2.2.1 - Dissemination material 2-NA2 10-INFN NA2.2 Pina Salente Pina Salente 3(Jul-10) Sept-10  
Yes / Done MS23 MSA2.2 - Continuous integration and certification testbeds in place 4-SA2 10-INFN SA2.6 Danilo Dongiovanni Danilo Dongiovanni 3(Jul-10) Nov-10  
DONE MS3 MNA1.3 - Technical collaboration procedures with EGI and PRACE are established 1-NA1 1-CERN NA1.7 Alberto Di Meglio Alberto Di Meglio 3(Jul-10) Nov-10  
DONE MS38 MJRA1.13 - Agreement on common information exchange methods 5-JRA1 1-CERN JRA1.5 Laurence Field Laurence Field 3(Jul-10) Feb-11  
DONE MS41 MJRA1.16 - Recommendation of a common set of standards relevant to EMI 5-JRA1 19-UIO JRA1.6 Aleksandr Konstantinov Aleksandr Konstantinov 3(Jul-10)    
DONE MS30 MJRA1.5 - Agreement on common security methods for data systems 5-JRA1 1-DESY JRA1.3 Patrick Fuhrmann Patrick Fuhrmann 5(Sep-10) Feb-11 Moved to end of 2010
DONE MS14 MNA2.3.1 - Training material and on-line courses 2-NA2 15-TCD NA2.3 Kathryn Cassidy Kathryn Cassidy 6(Oct-10) Feb-11  
DONE MS18 MSA1.2.1 - EMI Reference Releases 3-SA1 10-INFN SA1.3 Cristina Aiftimiei Cristina Aiftimiei 6(Oct-10 ) Feb-11  
DONE MS24 MSA2.3 - Large-scale acceptance certification testbeds are in place 4-SA2 10-INFN SA2.6 Danilo Dongiovanni Danilo Dongiovanni 6(Oct-10) Feb-11  
DONE MS27 MJRA1.2 - Agreement on common job submission and management methods 5-JRA1 10-INFN JRA1.2 Massimo Sgaravatto Massimo Sgaravatto 6(Oct-10) Feb-2011 Moved to end of 2010
DONE MS4 MNA1.4.1 - Service Level Agreements in place 1-NA1 1-CERN NA1.5 Alberto Di Meglio Alberto Di Meglio 6(Oct-10) 14/04/2011  
Yes / Done MS34 MJRA1.9 - AAI requirements of DCIs 5-JRA1 18-UH JRA1.4 John White John White 7(Nov-10) Sep-10  
DONE MS44 MJRA1.19.1 - Integrated EMI Major Release Candidates 5-JRA1 8-JUELICH JRA1.7 Morris Riedel
Cristina Aiftimiei
Morris Riedel
Cristina Aiftimiei
10(Feb-11) 07/06/2011  
DONE MS12 MNA2.2.2 - Dissemination material 2-NA2 10-INFN NA2.2 Pina Salente Pina Salente 12(Apr-11) 30/04/2011  
DONE MS19 MSA1.2.2 - EMI Reference Releases 3-SA1 10-INFN SA1.3 Cristina Aiftimiei Cristina Aiftimiei 12(Apr-11) 12/05/2011  
DONE MS25 MSA2.4 - Software development tools aligned across activities, partners and middleware stacks 4-SA2 1-CERN SA2.5 Jozef Cernak Jozef Cernak 12(Apr-11) 30/04/2011  
DONE MS39 MJRA1.14 - EMI Information exchange used in computing 5-JRA1 1-CERN JRA1.5 Laurence Field Laurence Field 12(Apr-11) 30/04/2011  

Status Number Title WP number Lead Beneficiary Task Number Task Leader Author Due Date Achievement Date Notes
DONE MS7 MNA1.5.1 -Successful completion of the periodic and final reviews 1-NA1 1-CERN NA1.1 Alberto Di Meglio Alberto Di Meglio 14(Jun-11) Jun-11  
DONE MS31 MJRA1.6 - File Catalogue common front-ends 5-JRA1 6-DESY JRA1.3 Patrick Fuhrmann Patrick Fuhrmann 15(Jul-11) 02/09/11  
DONE MS35 MJRA1.10 - EMI Security Workshop 5-JRA1 18-UH JRA1.4 John White John White 17(Sep-11) 21/09/2011  
DONE MS15 MNA2.3.2 - Training material and on-line courses 2-NA2 15-TCD NA2.3 Kathryn Cassidy Kathryn Cassidy 18(Oct-11)    
DONE MS47 MNA3.1 - EMI Product Suite FactSheets available on EMI Website 6-NA3 8-JUELICH NA3.1 Morris Riedel Morris Riedel 20(Dec-11) 31/12/2011 Report:
27/05/2012
DONE MS28 MJRA1.3 - Successful implementation of the common job submission and management methods 5-JRA1 10-INFN JRA1.2 Marco Cecchi Marco Cecchi 21(Jan-12)    
DONE MS48 MNA3.2 - Open Source Software Initiative Charter exists 6-NA3 12-NIIFI NA3.2 Peter Stefan Peter Stefan 23(Mar-12)    
DONE MS49 MNA3.3.1 - EMI Product Use Cases are documented 6-NA3 8-JUELICH NA3.1 Morris Riedel Morris Riedel 23(Mar-12) 31/03/2012 Report:
27/05/2012
DONE MS51 MNA3.4.1PGI/BES/JSDL/UR Specification Draft exist 6-NA3 8-JUELICH NA3.1 Morris Riedel Morris Riedel 23(Mar-12) 31/03/2012  
DONE MS5 MNA1.4.2 - Service Level Agreements in place 1-NA1 1-CERN NA1.5 Alberto Di Meglio Alberto Di Meglio 24(Apr-12)    
DONE MS45 MJRA1.19.2 - Integrated EMI Major Release Candidates 5-JRA1 11-LU JRA1.1 Balazs Konya Balazs Konya 22(Feb-12) 29/02/2012 Report 27/05/2012
DONE MS13 MNA2.2.3 - Dissemination material 2-NA2 10-INFN NA2.2 Pina Salente Pina Salente 24(Apr-12) 30/04/2012 Report:
24/05/2012
DONE MS20 MSA1.2.3 - EMI Reference Releases 3-SA1 10-INFN SA1.3 Cristina Aiftimiei Cristina Aiftimiei 24(Apr-12)    
DONE MS32 MJRA1.7 - First implementations of POSIX compliance and HTTP support 5-JRA1 6-DESY JRA1.3 Patrick Fuhrmann Patrick Fuhrmann 24(Apr-12) 31/03/2012 Report:
27/05/2012
Delayed to P3 MS37 MJRA1.12 - Common Security Architecture Assessment 5-JRA1 18-UH JRA1.4 John White John White 24(Apr-12)    

Status Number Title WP number Lead Beneficiary Task Number Task Leader Author Due Date Achievement Date Notes
DONE MS37 MJRA1.12 - Common Security Architecture Assessment 5-JRA1 18-UH JRA1.4 John White John White 24(Apr-12)   Report:
23/04/13
DONE MS8 MNA1.5.2 -Successful completion of the periodic and final reviews 1-NA1 1-CERN NA1.1 Alberto Di Meglio Alberto Di Meglio 26(Jun-12) 12/06/2012 Report:
29/10/2012
DONE MS16 MNA2.3.3 - Training material and on-line courses 2-NA2 15-TCD NA2.3 Kathryn Cassidy Kathryn Cassidy 30(Oct-12) 31/10/2012 Report:
06/11/12
DONE MS33 MJRA1.8 - Full standard compliance and POSIX support 5-JRA1 6-DESY JRA1.3 Patrick Fuhrmann Patrick Fuhrmann 30(Oct-12) 31/10/2012 Report:
06/11/12
DONE MS42 MJRA1.17 -Test suites of compliance checks in place 5-JRA1 19-UIO NA3.3 Jon K. Nilsen Jon K. Nilsen 30(Oct-12)   Report:
15/02/13
DONE MS43 MJRA1.18 - Transparent use of open standards in the EMI component ecosystem 5-JRA1 19-UIO JRA1.6 Weizhong Qiang Weizhong Qiang 30(Oct-12)   Report:
11/02/13
DONE MS29 MJRA1.4 - Successful computational usage of emerging computing models 5-JRA1 10-INFN JRA1.2 Marco Cecchi Marco Cecchi 32(Dec-12)   Report:
19/12/12
DONE MS36 MJRA1.11 - Easier end-user access capability to EMI components in place 5-JRA1 18-UH JRA1.4 John White John White 32(Dec-12)    
DONE MS40 MJRA1.15 - Service monitoring and management 5-JRA1 1-CERN JRA1.5 Laurence Field Laurence Field 32(Dec-12)   Report:
12/12/12
DONE MS46 MJRA1.19.3 - Integrated EMI Major Release Candidates 5-JRA1 11-LU JRA1.1 Balazs Konya Balazs Konya 32(Dec-12)   Report:
29/01/13
DONE MS50 MNA3.3.2 - EMI Product Use Cases are documented 6-NA3 8-JUELICH NA3.1 Morris Riedel Morris Riedel 35(Mar-13)    
DONE MS52 MNA3.4.2 - PGI/BES/JSDL/UR Final Specification exist 6-NA3 8-JUELICH NA3.1 Morris Riedel Morris Riedel 35(Mar-13)    
DONE MS53 MNA3.5 - Future Plans of the Open Source Software Initiative documented 6-NA3 12-NIIFI NA3.2 Alberto Di Meglio Alberto Di Meglio 35(Mar-13)   Report:
15/04/13
DONE MS54 MNA3.6 - The use of EMI products by new user communities is documented 6-NA3 8-JUELICH NA3.1 Morris Riedel Morris Riedel 35(Mar-13)    
DONE MS21 MSA1.2.4 - EMI Reference Releases 3-SA1 10-INFN SA1.3 Cristina Aiftimiei Cristina Aiftimiei 36(Apr-13)   Report:
21/04/13
DONE MS6 MNA1.4.3 - Service Level Agreements in place 1-NA1 1-CERN NA1.5 Alberto Di Meglio Alberto Di Meglio 36(Apr-13)    
  MS9 MNA1.5.3 - Successful completion of the periodic and final reviews 1-NA1 1-CERN NA1.1 Alberto Di Meglio Alberto Di Meglio 36(Apr-13)    
Edit | Attach | Watch | Print version | History: r108 < r107 < r106 < r105 < r104 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r108 - 2013-05-27 - unknown
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    EMI All webs login

This site is powered by the TWiki collaboration platform Powered by PerlCopyright &© 2008-2024 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
or Ideas, requests, problems regarding TWiki? use Discourse or Send feedback