Productive Hours

Productive hours must be calculated according to the beneficiary's normal practices. The annual number of productive hours can be calculated in two ways:

  • by using a standard number of productive hours used for all employees;
  • by calculating an actual individual number of productive hours for each employee.

Productive hours per year should exclude annual leave, public holidays, training and sick leave.

Example:

Total days in a year 365
Weekends            -104
Annual holidays     -21
Statutory holidays  -15
Illness/Others      -15
Workable days in a year 210

Productive hours in a year:  210 x 8 hours/day = 1680 hours

Some activities may be considered not to be part of the productive hours of personnel:

  • Training (not project related)
  • Internal meetings (not project related)


Personnel Hourly Rates

The beneficiary can not claim more hours than the ones he used for the computation of the personnel hourly rates.

Example:

Total productive hours = 210 days x 7,5 hours = 1570 hours
Total Salary (statutory costs, including holiday pay, etc...) = 30,000 EUR/year
Personnel Hourly rate = 30,000 EUR / 1570 hours = 19,1 EUR/hour
Total hours worked for the project = 650 hours
Total costs charged to the project = 650 hours x 19,1 EUR/hour = 12,415 EUR

Source: Guide to Financial Issues relating to FP7 Indirect Actions

-- FloridaEstrella - 02-Jul-2010

Edit | Attach | Watch | Print version | History: r3 < r2 < r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r3 - 2010-07-05 - unknown
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    EMI All webs login

This site is powered by the TWiki collaboration platform Powered by PerlCopyright &© 2008-2024 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
or Ideas, requests, problems regarding TWiki? use Discourse or Send feedback