HarryRenshall - 06 Mar 2006
CERN (Tier 0) Overall Resource Requirements Timetable for 2006
See the attached word document of B.Panzer at:
https://twiki.cern.ch/twiki/pub/LCG/CernPlans/ResourceallocationplanningforCERNin2006__v4.doc
CERN (Tier 0) SC4 Resource Requirements Timetable for 2006
April 3rd (Monday) - April 16th (Thursday before Easter) - sustain an average daily rate to each Tier1 at or above the full nominal diskdisk rate below.
From Tuesday April 18th - Monday April 24th we should perform the disk-tape tests at the rates in the table below. Any loss of average rate to a site of greater or equal to 10% should be
accounted for (e.g. by an explanation/resolution in the operations log)
and compensated for by a corresponding increase in rate in the following days.
Site |
Disk-Disk |
Disk-Tape |
ASGC |
100 |
75 |
TRIUMF |
50 |
50 |
BNL |
200 |
75 |
FNAL |
200 |
75 |
NDGF |
50 |
50 |
PIC |
60* |
60 |
RAL |
150 |
75 |
SARA |
150 |
75 |
IN2P3 |
200 |
75 |
FZK |
200 |
75 |
CNAF |
200 |
75 |
- The nominal rate for PIC is 100MB/s, but will be limited by the WAN until ~November 2006.
From 1 May CERN to the end of September CERN will top up the data rates to all Tier 1 sites to the disk-disk rates as above. From October the proposal is to switch to disk-tape mode at the above disk-tape rates.