LCG Planning Check Lists
Modified on: 2006-01-13
The check lists in this page are intended as help to improve the existing LCG milestone plans.
All projects should contain the information requested in the appropriate check list.
Please specify in your plan each of the items and sub items and when it occurs. If some item does not apply to your plan specify so explicitly as a note in the plan.
Mail me if you have improvements to the list(s) below.
Grid Sites
Use this check list to complete the
Tier-1 and Tier-2 sites plans.
- CPU procurement
- decisions, orders, start install, end install, operational
- Disk procurement
- decisions, orders, start install, end install, operational
- Tape procurement
- robots, tape drives, tape servers, tape cartridges, decisions, orders, start install, end install, operational
- Network equipment
- hardware, routers, hw for connection to T0, hw for connections to T2s, plan, testing, operational
- Service Challenges
- performance and capacity milestones
- Connection to T0
- deliver plan, begin testing, different tests, operational
- Connections to T1s
- deliver plan, begin testing, different tests, operational
- Connections to T2s
- deliver plan, begin testing, different tests, operational
- Human resources
- hiring, operational
- 24/7 On-Call System
- definition of procedures, hiring, operational
- Infrastructure work, electricity, airconditioning, safety, etc
- begin work, operational
- VOBoxes installed
- for each experiment, versions, installation, begin testing and operational
- LFC upgraded
- versions, installation, testing, operational
- FTS installed
- version, when installed, operational
- SRM system
- Castor2, dCache or DPM: installation, testing, operational, future expansions
- 3D project
- Hardware procurement, installation, testing, operational
- Other services deployed
- RB, BDII, RGMA, etc: versions, installation, testing, operational
Areas and Services projects
To be provided. Feel free to edit this page and add a check list.
Experiments
To be provided. Feel free to edit this page and add a check list.