LCG Planning Check Lists
Grid Sites
Use this check list to complete the
Tier-1 and Tier-2 sites plans.
- CPU procurement
- decisions, orders, start install, end install, operational
- Disk procurement
- decisions, orders, start install, end install, operational
- Tape procurement
- robots, tape drives, tape servers, tape cartridges, decisions, orders, start install, end install, operational
- Network equipment
- hardware, routers, hw for connection to T0, hw for connections to T2s, plan, testing, operational
- Service Challenges
- performance and capacity milestones
- Connection to T0
- deliver plan, begin testing, different tests, operational
- Connections to T1s
- deliver plan, begin testing, different tests, operational
- Connections to T2s
- deliver plan, begin testing, different tests, operational
- Human resources
- hiring, operational
- 24/7 On-Call System
- definition of procedures, hiring, operational
- Infrastructure work, electricity, airconditioning, safety, etc
- begin work, operational
- VOBoxes installed
- for each experiment, versions, installation, begin testing and operational
- LFC upgraded
- versions, installation, testing, operational
- FTS installed
- version, when installed, operational
- SRM system
- Castor2, dCache or DPM: installation, testing, operational, future expansions
- 3D project
- Hardware procurement, installation, testing, operational
- Other services deployed
- RB, BDII, RGMA, etc: versions, installation, testing, operational
Areas and Services projects
To be provided. Feel free to edit this page and add a check list.