HarryRenshall - 31 Oct 2007
TRIUMF-Vancouver Site Capacity Growth Plans 2007/2008
Last Updated 5.11.2007: email of 2 November from Reda Tafirout <tafirout@triumf.ca>
Effectively we have on the floor already all of our 2007+2008 CPU + TAPE
requirements (
MoU numbers), for the disk our 2008 portion is expected to be
delivered by the end of November/early December, so it will be in ready for
production in January.