Meetings of the PS Booster Upgrade Working Group

Main LIU-PSB Meetings

Links to some of the main LIU Meetings

Links to PSB relevant meetings

Action List/Milestones

  • PSB Energy Upgrade Working Group: Open Actions, the remaining open actions are followed by the LIU-PSB Technical Coordination.

Minutes of Meetings

LIU-PSB Technical Coordination Meeting (Indico Page)

Date Title Agenda Minutes Link to presentation(s)
23.09.2019 Ad-Hoc Meeting 5: Alignment BT-BTM-BTP (Agenda) (Minutes)  
21.08.2019 Ad-Hoc Meeting 4: EN-CV Specs for Temporary Solution for PSB Tests (Agenda) (Minutes) EN-CV Specifications for Temporary Solution for PSB Tests, D. Hay
24.06.2019 Ad-Hoc Meeting 3: BI/BT Line Drawings/Marking/Drilling (Agenda) (Minutes) BI Line Verification, J.P. Corso
BI Transfer Line Checks, C. Bracco
03.06.2019 Ad-Hoc Meeting 2: BI/BT Line Drawings/Marking/Drilling (Agenda) (Minutes) Status BI/BT Line Drawings/Marking/Drilling, M. Atanasov
29.05.2019 Ad-Hoc Meeting 1: EN-CV LS2 Activities on Critical Path (Agenda) (Minutes) EN-CV: Brief Status and Issues, D. Hay
28.05.2019 LIU-PSB TCM 3 (Agenda) (Minutes) PSB LS2 Shutdown Activities: Brief Status and Issues, D. Hay
IST Preparation, F. Chapuis
19.02.2019 LIU-PSB TCM 2 (Agenda) (Minutes) Injection Area 1L1, W. Weterings
05.02.2019 LIU-PSB TCM 1 (Agenda) (Minutes) Project re-organisation, G.P. Di Giovanni
PSB LS2 Activities, D. Hay

PS Booster Upgrade Working Group (Indico Page)

Date Title Agenda Minutes Link to presentation(s)
04.12.2018 PS Booster Upgrade Working Group Meeting 226 (Agenda) (Minutes) Linac4-to-PSB LS2 schedule, J. Coupard
Update on the ECRs, T. Birtwistle
06.11.2018 PS Booster Upgrade Working Group Meeting 225 (Agenda) (Minutes) WPA and PSB master schedule, D. Hay
Update on the ECRs, T. Birtwistle
23.10.2018 PS Booster Upgrade Working Group Meeting 224 (Agenda) (Minutes) Commissioning of the new PSB wire scanner, J. L. Sirvent Blasco
EVM report, S. Prodon
09.10.2018 PS Booster Upgrade Working Group Meeting 223 (Agenda) (Minutes) Transmission measurement of all the PSB machine, F. Schmidt
25.09.2018 PS Booster Upgrade Working Group Meeting 222 (Agenda) (Minutes) TE-VSC activities and status, J. A. Ferreira Somoza
Status of the ECRs, T. Birtwistle
11.09.2018 PS Booster Upgrade Working Group Meeting 221 (Agenda) (Minutes) Status of the electrical and pressure conformity files, A. Funken
TE-MSC activities and status, A. Newborough
LIU-PSB EVM status, S. Prodon
28.08.2018 PS Booster Upgrade Working Group Meeting 220 (Agenda) (Minutes) Status of the LIU-PSB Safety File and next steps, A. Funken
EN-CV activities and status, G. Petrika
PSB and Linac 4 Applications Development during LS2, J-F. Comblin
31.07.2018 PS Booster Upgrade Working Group Meeting 219 (Agenda) (Minutes) EN-EL activities and status and post mortem analysis during YETS, J. Devine
Signal and DC cabling and de-cabling activities, G. Minchev Georgiev
Status of the ECRs and integration studies, T. Birtwistle and Y. Muttoni
17.07.2018 PS Booster Upgrade Working Group Meeting 218 (Agenda) (Minutes) EN-CV Activities in B245, J-P. Rodary
Report on the ECRs for LS2, T. Birtwistle
03.07.2018 PS Booster Upgrade Working Group Meeting 217 (Agenda) (Minutes) Update on the POPs-B, F. Boattini
19.06.2018 PS Booster Upgrade Working Group Meeting 216 (Agenda) (Minutes) WP analysis for LS2, D. Hay
Report on the ECRs for LS2, T. Birtwistle
22.05.2018 PS Booster Upgrade Working Group Meeting 215 (Agenda) (Minutes) Status of H0/H- Electronics, SEM Grids in LBE and PSB WS Prototype, F. Roncarolo
Report on the ECRs for LS2, T. Birtwistle
08.05.2018 PS Booster Upgrade Working Group Meeting 214 (Agenda) (Minutes) EVM PSB Update, S. Prodon
Report on the ECRs for LS2, T. Birtwistle
17.04.2018 PS Booster Upgrade Working Group Meeting 213 (Agenda) (Minutes) LN-to-PSB connection project, A. Berjillos Barranco
Report on the ECRs for LS2, T. Birtwistle
PSB Transmission Line Measurements, F. Schmidt
03.04.2018 PS Booster Upgrade Working Group Meeting 212 (Agenda) (Minutes) Q-strip specifications with respect to beam dynamics F. Antoniou
LIU PSB Q-strip power converters L. De Mallac
20.03.2018 PS Booster Upgrade Working Group Meeting 211 (Agenda) (Minutes) POPs-B power converter report, F. Boattini
Update on the design of the BTP stopper, E. Grenier-Boley
Report on the ECRs for LS2, T. Birtwistle
06.03.2018 PS Booster Upgrade Working Group Meeting 210 (Agenda) (Minutes) Report on the LS2 schedule, D. Hay
Transformers: intervention scenarios and spare policy, D. Aguglia
Final LS2 readiness document, J. Coupard
Report on the ECRs for LS2, T. Birtwistle
20.02.2018 PS Booster Upgrade Working Group Meeting 209 (Agenda) (Minutes) LIU-PSB MDS and studies: 2018, S. Albright
Follow-up on the Installation Readiness for LS2, J. Coupard
Follow-up on the ECR for LS2, T. Birtwistle
EVM PSB Update, S. Prodon
06.02.2018 PS Booster Upgrade Working Group Meeting 208 (Agenda) (Minutes) POPS-B project follow-up, F. Boattini
PSB Heating system removal YETS pilot project & LS2 , G. Petrika
16.01.2018 PS Booster Upgrade Working Group Meeting 207 (Agenda) (Minutes) Thermomechanical simulations on the PSB scraper, I. Lamas Garcia
Preliminary design of the BTP line, B. Riffaud
LIU-PSB EVM Update, S. Prodon
05.12.2017 PS Booster Upgrade Working Group Meeting 206 (Agenda) (Minutes) Update on B-train measurements, M. Buzio
Proposal of vacuum chambers for BHZ151 and associated magnets, J. A. Ferreira Somoza
21.11.2017 PS Booster Upgrade Working Group Meeting 205 (Agenda) (Minutes) Update on the heating system removal intervention in the PSB tunnel, G. Petrika
Building 245 – État général des travaux génie civil, H. Botella Esteban
LIU-PSB EVM Status, S. Prodon
07.11.2017 PS Booster Upgrade Working Group Meeting 204 (Agenda) (Minutes) PS Complex Layout Database Refurbishment and Post-LS2 Version, T. Birtwistle
Injector Optics Repository - Status Update, I. Efthymiopoulos
24.10.2017 PS Booster Upgrade Working Group Meeting 203 (Agenda) (Minutes) TFB Update, A. Blas
LIU-PSB EVM Update, S. Prodon
10.10.2017 PS Booster Upgrade Working Group Meeting 202 (Agenda) (Minutes) Cabling for YETS 17-18 in PSB, G. M. Georgiev
New BPM in the BI line, C. Hessler
ECR for the coming YETS and LS2, J. Coupard
26.09.2017 PS Booster Upgrade Working Group Meeting 201 (Agenda) (Minutes) Current Status of the PSB Scraper Study, I. Lamas Garcia
LIU-PSB EVM Update, S. Prodon
Injection Q-strips, L. De Mallac
12.09.2017 PS Booster Upgrade Working Group Meeting 200 (Agenda) (Minutes) Update on the BPM in the BI line request, K. Hanke
29.08.2017 PS Booster Upgrade Working Group Meeting 199 (Agenda) (Minutes) Report on the Installation of the New Wirescanner during TS3, R. Veness
LIU-PSB EVM Update, S. Prodon
Follow-up on the Installation Readiness for LS2, J. Coupard
Additional BPMs in the PSB Transfer Lines, G. P. Di Giovanni
01.08.2017 PS Booster Upgrade Working Group Meeting 198 (Agenda) (Minutes) Update on the PSB Cooling and Ventilation Systems G. Petrika
18.07.2017 PS Booster Upgrade Working Group Meeting 197 (Agenda) (Minutes) Update on the PSB Transfer Lines C. Hessler
04.07.2017 PS Booster Upgrade Working Group Meeting 196 (Agenda) (Minutes) Follow-up on the B-train M. Buzio
20.06.2017 PS Booster Upgrade Working Group Meeting 195 (Agenda) (Minutes) Status of SEM Grids for Injection Matching J. Tan
LIU-PSB EVM S. Prodon
06.06.2017 PS Booster Upgrade Working Group Meeting 194 (Agenda) (Minutes) RF bypass measurements in PS with high intensity beams J. Ferreira Bento
23.05.2017 PS Booster Upgrade Working Group Meeting 193 (Agenda) (Minutes) Follow up of the new PSB injection from the HST W.Weterings
B245 Modifications and Cabling Update F. Boattini
09.05.2017 PS Booster Upgrade Working Group Meeting 192 (Agenda) (Minutes) RF bypass impedence measurements, J. Ferreira Bento
Update on the recombination kickers, V. Forte, L. Sermeus
Linac4 connection, K. Hanke
LIU-PSB EVM, S. Prodon
ECR status for Linac4 connection, A. Berjillos Barranco, J. Coupard
25.04.2017 PS Booster Upgrade Working Group Meeting 191 (Agenda) (Minutes) BLMs installation status, C. Zamantzas
11.04.2017 PS Booster Upgrade Working Group Meeting 190 (Agenda) (Minutes) BT, BTM and BTP integration, J-M Lacroix
Cancel MPS ripples with BDLs, I. Josifovic
28.03.2017 PS Booster Upgrade Working Group Meeting 189 (Agenda) (Minutes) Booster MDs, F. Schmidt
LIU-PSB EVM Status, S. Prodon
14.03.2017 PS Booster Upgrade Working Group Meeting 188 (Agenda) (Minutes) Thermo-structural analysis on a UHV gate valve, A. Pilan Zanoni
28.02.2017 PS Booster Upgrade Working Group Meeting 187 (Agenda) (Minutes) BRF2-bunker PSB, A. Martinez Selles
21.02.2017 PS Booster/PS Upgrade Working Group Meeting 3 (Agenda) (Minutes) The PSB, PS and TL Optics Repositories, I. Efthymiopoulos
07.02.2017 PS Booster Upgrade Working Group Meeting 186 (Agenda) (Minutes) Feedback from POPS Explosion Analysis, F. Boattini
De-cabling & cabling during EYETS 16-17 in the Booster, G. M. Georgiev
17.01.2017 PS Booster Upgrade Working Group Meeting 185 (Agenda) (Minutes) Recombination Kicker Rise Time, L. Sermeus
Recombination Kicker Waveform Measurements, V. Forte
06.12.2016 PS Booster Upgrade Working Group Meeting 184 (Agenda) (Minutes) LIU-PSB Beam Dynamic Studies, E. Benedetto
22.11.2016 PS Booster Upgrade Working Group Meeting 183 (Agenda) (Minutes) TE/VSC Simulation of the New Beam Scraper/Absorber, J. Hansen
Thermo-structural Analysis on a UHV Gate Valve Hit by LIU-PSB Beam, A. Pilan-Zanoni
Proposed Magnetic Cycle at 1.4 and 2 GeV, S. Albright
08.11.2016 PS Booster Upgrade Working Group Meeting 182 (Agenda) (Minutes) Review of BI Equipment for the Linac4-to-PSB Connection, J. Tan
01.11.2016 PS Booster/PS Upgrade Working Group Meeting 2 (Agenda) (Minutes) PSB RF Bypasses, A. Blas
PS RF Bypasses, H. Damerau
Plans for the New PSB B-Train during EYETS and BT.BHZ10 BTrain Option, M. Buzio
Status of the LLRF for the New PS B-Train System, D. Perrelet
04.10.2016 PS Booster Upgrade Working Group Meeting 181 (Agenda) (Minutes) Status/Preparation of the Control Applications for L4-to-PSB Connection, J. Sanchez-Alvarez
Synchronization between Linac4 and PSB, E. Benedetto
20.09.2016 PS Booster Upgrade Working Group Meeting 180 (Agenda) (Minutes) PSB Injection Mock-up Area/Stripping Foil Test Stand, W. Weterings
06.09.2016 PS Booster Upgrade Working Group Meeting 179 (Agenda) (Minutes) Material Choice for the Vacuum Window at the Exit of BTM, C. Di Paolo
EN-STI Activities in the Framework of LIU-PSB, I. Garcia Lamas
16.08.2016 PS Booster Upgrade Working Group Meeting 178 (Agenda) (Minutes) HST Hardware Installation and Commissioning, G. Guidoboni
19.07.2016 PS Booster Upgrade Working Group Meeting 177 (Agenda) (Minutes) Recombination Kicker Rise Time, L. Sermeus
Recombination Kicker Waveform Measurements, V. Forte
05.07.2016 PS Booster Upgrade Working Group Meeting 176 (Agenda) (Minutes) Cabling Commitment for LIU-PSB during EYETS, G.M. Georgiev
PSB Beam Scrapers/Absorbers: Thermo-Mechanical Simulations, I. Lamas Garcia
07.06.2016 PS Booster Upgrade Working Group Meeting 175 (Agenda) (Minutes) LS2 Master Schedule, J. Coupard
POPS-B Project Update and Feedback from POPS Experience, F. Boattini
TFB Amplifier Prototype, M. Paoluzzi
24.05.2016 PS Booster Upgrade Working Group Meeting 174 (Agenda) (Minutes) Status of the Safety Files, L. Kobzeva
Forecasts for Waste and Radioactive Material Storage, L. Kobzeva
10.05.2016 PS Booster Upgrade Working Group Meeting 173 (Agenda) (Minutes)  
03.05.2016 PS Booster/PS Upgrade Working Group Meeting 1 (Agenda) (Minutes) Complementary Measurements on the Main Dipole for the Booster B-Train System, A. Beaumont
B-Train System, M. Buzio
19.04.2016 PS Booster Upgrade Working Group Meeting 172 (Agenda) (Minutes) ECR/SSR for EYETS 2016/2017, J. Coupard
PSB Beam Absorber/Scraper After LS2, M. Kowalska
PSB Beam Absorber/Scraper After LS2, F.X. Nuiry
05.04.2016 PS Booster Upgrade Working Group Meeting 171 (Agenda) (Minutes) PSB RF System Upgrade Availability Studies, O. Rey Orozco
Field Control of TL Switching Dipole, M. Buzio
22.03.2016 PS Booster Upgrade Working Group Meeting 170 (Agenda) (Minutes) MD Planning in 2016 for LIU-PSB, E. Benedetto
EPC Planned Work for EYETS 2016, S. Pittet,
PSB-PS Magnets Specifications, W. Bartmann
08.03.2016 PS Booster Upgrade Working Group Meeting 169 (Agenda) (Minutes) Alignment Changes in the PSB after YETS 2015/2016, G.P. Di Giovanni
Review of the Present Issues in the Alignment the PSB Equipment, T. Dobers
Longitudinal Dynamic Simulations of PSB Beams in the LINAC4 Scenario, D. Quartullo
23.02.2016 PS Booster Upgrade Working Group Meeting 168 (Agenda) (Minutes) Handling of Magnets BT.BHZ10 and BTM.BHZ10, C. Bertone
Removal of CV Pipes in the PSB Injection Region, N. Roget
09.02.2016 PS Booster Upgrade Working Group Meeting 167 (Agenda) (Minutes) Status of the PSB Transverse Feedback A. Blas
19.01.2016 PS Booster Upgrade Working Group Meeting 166 (Agenda) (Minutes) Recombination Kicker Rise Time, L. Sermeus
Review of the Optics of the PSB Extraction Lines, J. Abelleira
Quadrupoles Trims for 2 GeV Operation/Tunes at Extraction, E. Benedetto
10.12.2015 PS Booster Upgrade Working Group Meeting 165 (Agenda) (Minutes) Finement Project Review and Planning, M. Paoluzzi
26.11.2015 PS Booster Upgrade Working Group Meeting 164 (Agenda) (Minutes) Status of the PSB Extraction and Recombination Septa and Kickers, J. Borburgh
12.11.2015 PS Booster Upgrade Working Group Meeting 163 (Agenda) (Minutes) Injection Tests with Carbon Foils in ISIS, B. Jones
05.11.2015 PS Booster Upgrade Working Group Meeting 162 (Agenda) (Minutes) Magnetic Measurement on PSB Dipoles Main and Injection Type, R. Chritin
PSB BHZ Main Magnets and the Required Trims, A. Newborough
Status of PSB B-train System Upgrade, M. Buzio
22.10.2015 PS Booster Upgrade Working Group Meeting 161 (Agenda) (Minutes) Discussion about Review of the Present Issues in Alignment the PSB Equipment , T. Dobers
Integration Issues of the BT-BTM-BTP Line, J.M. Lacroix
Optics Changes Needed to Address the Integration Issues of the BT-BTM-BTP Line, J. Abelleira
08.10.2015 PS Booster Upgrade Working Group Meeting 160 (Agenda) (Minutes) Pumping in Sections 4L1 and 11L1 for the Installation of the New Wire Scanners, F. Salveter
Exchange Procedure for the Stripping Foil, W. Weterings
Status of the Test Stand of the Stripping Foil, W. Weterings
24.09.2015 PS Booster Upgrade Working Group Meeting 159 (Agenda) (Minutes) Review of the Optics of the PSB Extraction Lines, J. Abelleira
Stability Studies of the PSB-PS Extraction Line, W. Bartmann
17.09.2015 PS Booster Upgrade Working Group Meeting 158 (Agenda) (Minutes) Requests to EN/EL for the LIU-PSB, G.M. Georgiev
Status of the Ongoing Activities in B245, L.A. Lopez-Hernandez
Status Report about Installation, Transport and Handling, C. Bertone
03.09.2015 PS Booster Upgrade Working Group Meeting 157 (Agenda) (Minutes) Requests to EN/EL for the LIU-PSB, G.M. Georgiev
Rack Layout for the Finemet Cavities, M. Haase
Planning of the LIU-PSB Activities (YETS/EYETS/LS2), J. Coupard
27.08.2015 PS Booster Upgrade Working Group Meeting 156 (Agenda) (Minutes) Requests to EN/EL for the LIU-PSB, G.M. Georgiev
Discussion about the ECR PSB-LJ-EC-0001, O. Berrig
Results from the LV Measurement Campaign, J. Devine
06.08.2015 PS Booster Upgrade Working Group Meeting 155 (Agenda) (Minutes) Follow-up of the Shielding Simulation for the HST, M. Morgenstern
16.07.2015 PS Booster Upgrade Working Group Meeting 154 (Agenda) (Minutes) Requests to EN/EL for the LIU-PSB, G.M. Georgiev
Discussion about Review of the Present Issues in Alignment the PSB Equipment , T. Dobers.
02.07.2015 PS Booster Upgrade Working Group Meeting 153 (Agenda) (Minutes) Requests to EN/EL for the LIU-PSB, G.M. Georgiev
Status of the Beam Intercepting Devices Equipment for the 2.0 GeV Upgrade, D. Grenier
Alternative Solution for the Vacuum Window at the Exit of BTM and Experience with the Beam Dump Temperature Measurements, A. Perillo Marcone
25.06.2015 PS Booster Upgrade Working Group Meeting 152 (Agenda) (Minutes) Warm Magnet Interlock System, M. Zerlauth
Requests to EN/EL for the LIU-PSB G.M. Georgiev
18.06.2015 PS Booster Upgrade Working Group Meeting 151 (Agenda) (Minutes) BRF2 Integration Model Status, Y. Muttoni
Requests to EN/EL for the LIU-PSB, G.M. Georgiev
Organization for LIU: Power Distribution, J. Devine
Shielding Simulation for the HST M. Morgenstern
04.06.2015 PS Booster Upgrade Working Group Meeting 150 (Agenda) (Minutes) Safety Packages Proposal, K. Hanke
B245 Construction Status, K. Hanke
Requests to EN/EL for the LIU-PSB, G.M. Georgiev
PSB Finemet Cavities LS2 Rack Space Request, M. Haase
End-2016 Readiness for the Beam Interlock System, B.Puccio
End-2016 Readiness for the RF Bypasses and TFB Electronics, A. Blas
End-2016 Readiness for Controls, J. Betz
End-2016 Readiness for Applications, J. Sanchez-Alvarez
21.05.2015 PS Booster Upgrade Working Group Meeting 149 (Agenda) (Minutes) Progress on LIU-PSB Upgrade Work Activities, D. Hay
Collect Needs for Cooling And Ventilation, S. Moccia
Requests to EN/EL for the LIU-PSB, G.M. Georgiev
Status of Readiness for End-2016 Deadline for L4 Connection for WP 9.2, W. Weterings
Status of Readiness for End-2016 Deadline for L4 Connection, K. Hanke
07.05.2015 PS Booster Upgrade Working Group Meeting 148 (Agenda) (Minutes) Collect Needs for Cooling And Ventilation, S. Moccia,
Racks Space Allocation Layout of BRF2/BAT D. Hay
30.04.2015 PS Booster Upgrade Working Group Meeting 147 (Agenda) (Minutes) LIU-PSB Templates, G.P. Di Giovanni,
Requests to EN/EL for the LIU-PSB, G.M. Georgiev and J. Devine
16.04.2015 PS Booster Upgrade Working Group Meeting 146 (Agenda) (Minutes) List of BI Open Actions, G.P. Di Giovanni,
Activities YETS15-16 and Progress on LIU-PSB Upgrade Activities, D. Hay,
Collect Needs for Cooling And Ventilation, S. Moccia,
Collect Needs for Cabling, G. Minchev-Georgiev,
Qstrips Power Converters Specifications, L. De Mallac
26.03.2015 PS Booster Upgrade Working Group Meeting 145 (Agenda) (Minutes) Items Needed for L4 Connection, K. Hanke,
LIU BI.DIS Rise Time, L. Sermeus,
Measurement of the Current KFA Rise Time, L. Sermeus,
EN-MEF-SU Open Actions, T. Dobers
12.03.2015 PS Booster Upgrade Working Group Meeting 144 (Agenda) (Minutes) POPS-B, F. Boattini
26.02.2015 PS Booster Upgrade Working Group Meeting 143 (Agenda) (Minutes) Review of the readiness for the end-2016 deadline for the equipment for Linac4 connection.
12.02.2015 PS Booster Upgrade Working Group Meeting 142 (Agenda) (Minutes) End-2016 Readiness for the Equipment for Linac4, K. Hanke,
POPS-B, F. Boattini,
Status of the Half Sector Test, B. Mikulec
29.01.2015 PS Booster Upgrade Working Group Meeting 141 (Agenda) (Minutes) Review of the BI Equipment Installed for the LIU-PSB Upgrade, J. Tan
15.01.2015 PS Booster Upgrade Working Group Meeting 140 (Agenda) (Minutes) MADX and Aperture Studies for the BI Transfer Line, C. Bracco
04.12.2014 PS Booster Upgrade Working Group Meeting 139 (Agenda) (Minutes) Handling System for the PSB Reference Magnet in B361, C. Bertone,
Impact of Placing the PSB Reference Magnet in B245, F. Boattini
27.11.2014 PS Booster Upgrade Working Group Meeting 138 (Agenda) (Minutes) Status Report on the Integration of the PSB-PS Transfer Lines, J.-M. Lacroix
13.11.2014 PS Booster Upgrade Working Group Meeting 137 (Agenda) (Minutes) Functional Specifications Review for the Stripping Foil BSW Magnets Power Converters, D. Aguglia
06.11.2014 PS Booster Upgrade Working Group Meeting 136 (Agenda) (Minutes) Aperture Study on the PSB Extraction and Recombination Lines, J. Abelleira,
LIU-PSB Updated Budget Profiles K. Hanke & G.P. Di Giovanni
30.10.2014 PS Booster Upgrade Working Group Meeting 135 (Agenda) (Minutes) H- Injection into the ISIS Synchrotron, B. Jones. Extras: Image of foil change area at ISIS and ISIS Foil Change Procedure
16.10.2014 PS Booster Upgrade Working Group Meeting 134 (Agenda) (Minutes) PSB Reference Magnet, A. Newborough, and Booster B-train system upgrade, M. Buzio
09.10.2014 PS Booster Upgrade Working Group Meeting 133 (Agenda) (Minutes) LIU-PSB Budget Review, G.P. Di Giovanni & K. Hanke,
LIU-PSB Configuration Management, T. Birtwistle.
25.09.2014 PS Booster Upgrade Working Group Meeting 132 (Agenda) (Minutes) Building 245 - Civil engineering budget, A. Lopez-Hernandez and Rack Space Report, D. Hay.
04.09.2014 PS Booster Upgrade Working Group Meeting 131 (Agenda) (Minutes) BLMs integration in PSB H- injection system, B.Riffaud
21.08.2014 PS Booster Upgrade Working Group Meeting 130 (Agenda) (Minutes) LIU-PSB Work Breakdown Structure, K.Hanke
24.07.2014 PS Booster Upgrade Working Group Meeting 129 (Agenda) (Minutes) Aperture Checks for Different Linac4 Transfer Line Optics, C.Bracco
10.07.2014 PS Booster Upgrade Working Group Meeting 128 (Agenda) (Minutes)  
26.06.2014 PS Booster Upgrade Working Group Meeting 127 (Agenda) (Minutes) Handling of Critical Items for Transportation, J-L. Grenard
12.06.2014 PS Booster Upgrade Working Group Meeting 126 (Agenda) (Minutes) Localisation of Beam Losses in PSB, M. Kowalska, BLM Electronics Status, C. Zamantzas
22.05.2014 PS Booster Upgrade Working Group Meeting 125 (Agenda) (Minutes) Updated Status of the Impedance Model for the PSB, C.Zannini
08.05.2014 PS Booster Upgrade Working Group Meeting 124 (Agenda) (Minutes) New Optics of the PSB measurement line (BTM), W. Bartmann/J. Abelleira Fernandez
24.04.2014 PS Booster Upgrade Working Group Meeting 123 (Agenda) (Minutes) MDs Planning for 2014, E. Benedetto
10.04.2014 PS Booster Upgrade Working Group Meeting 122 (Agenda) (Minutes)  
27.03.2014 PS Booster Upgrade Working Group Meeting 121 (Agenda) (Minutes) New Cooling strategy for the B245, F. Boattini, M. Obrecht
13.02.2014 PS Booster Upgrade Working Group Meeting 120 (Agenda) (Minutes) Optics Measurements in the PSB, M. McAteer
30.01.2014 PS Booster Upgrade Working Group Meeting 119 (Agenda) (Minutes) Building 245 project update, F. Boattini
23.01.2014 PS Booster Upgrade Working Group Meeting 118 (Agenda) (Minutes) W. Weterings, New baseline design for the H0/H- beam dump
16.01.2014 PS Booster Upgrade Working Group Meeting 117 (Agenda) (Minutes)  
12.12.2013 PS Booster Upgrade Working Group Meeting 116 (Agenda) (Minutes)  
05.12.2013 PS Booster Upgrade Working Group Meeting 115 (Agenda) (Minutes) D. Hay, PSB Cranes renovation/replacement
07.11.2013 PS Booster Upgrade Working Group Meeting 114 (Agenda) (Minutes) Bulding 245 schedule update
24.10.2013 PS Booster Upgrade Working Group Meeting 113 (Agenda) (Minutes) Status of the RF
10.10.2013 Review of the PSB Ejection Lines @2GeV (Agenda) (Minutes) Optics of the Ejection Lines @2GeV and potential impact on hardware
09.10.2013 PSB injection sectorisation vs dump design   (Minutes)  
26.09.2013 PS Booster Upgrade Working Group Meeting 112 (Agenda) (Minutes) Beam dynamic: Inconel vacuum chamber
19.09.2013 PS Booster Upgrade Working Group Meeting 111 (Agenda) (Minutes) PSB H- Injection Vacuum Sectorisation
12.09.2013 PS Booster Upgrade Working Group Meeting 110 (Agenda) (Minutes)  
22.08.2013 PS Booster Upgrade Working Group Meeting 109 (Agenda) (Minutes) PSB Realignment Campaign
15.08.2013 PS Booster Upgrade Working Group Meeting 108 (Agenda) (Minutes) BLM cabling non-conformities
08.08.2013 PS Booster Upgrade Working Group Meeting 107 (Agenda) (Minutes) Configuration Management & ECRs
04.07.2013 PS Booster Upgrade Working Group Meeting 106 (Agenda) (Minutes) Report on ALARA committee and Status of New Main Dump
27.06.2013 PS Booster Upgrade Working Group Meeting 105 (Agenda) (Minutes) BTM Optics sutdies, Upgrade study of magnet BTM.BHZ 10
13.06.2013 PS Booster Upgrade Working Group Meeting 104 (Agenda) (Minutes) Rack space in 361, H0/H- review summary
30.05.2013 PS Booster Upgrade Working Group Meeting 103 (Agenda) (Minutes) Inconel vacuum chamber for injection section, Multipolar Effects, E.Benedetto, Impedance calculation, C. Zannini, Status of the layout, B. Riffaud
16.05.2013 PS Booster Upgrade Working Group Meeting 102 (Agenda) (Minutes) Design of BI.DHZ.DVT50/BI.DHZ.DVT70, L. Vanherpe
25.04.2013 PS Booster Upgrade Working Group Meeting 101 (Agenda) (Minutes) PSB with Linac 4 - RF matching, A. Blas
18.04.2013 Review on the H-/H0 dumps (Agenda) (Minutes) H0/H- dumps, H0/H- instrumentation, Vacuum systems, Radio protection
11.04.2013 PS Booster Upgrade Working Group Meeting 100 (Agenda) (Minutes) Status of the New PSB Main Dump; Dismantling of the Old PSB Dump
14.03.2013 PS Booster Upgrade Working Group Meeting 99 (Agenda) (Minutes) Injection Aperture Limitations, C. Bracco
07.03.2013 PS Booster Upgrade Working Group Meeting 98 (Agenda) (Minutes) LLRF : PSB ring inhibit in the Linac4 area, A. Blas
28.02.2013 PS Booster Upgrade Working Group Meeting 97 (Agenda) (Minutes) Beam Interlock System for transfer line and PSB, C. Martin
14.02.2013 PS Booster Upgrade Working Group Meeting 96 (Agenda) (Minutes) Design of Booster Injection Quadrupole magnets, A. Aloev
07.02.2013 PS Booster Upgrade Working Group Meeting 95 (Agenda) (Minutes) Optic Transfer Line L4 to PSB, A. Lombardi
31.01.2013 PS Booster Upgrade Working Group Meeting 94 (Agenda) (Minutes)  
17.01.2013 PS Booster Upgrade Working Group Meeting 93 (Agenda) (Minutes)  
13.12.2012 PS Booster Upgrade Working Group Meeting 92 (Agenda) (Minutes)  
29.11.2012 PS Booster Upgrade Working Group Meeting 91 (Agenda) (Minutes) Head/Tails and H-/H0 dumps dedicated meeting
22.11.2012 PS Booster Upgrade Working Group Meeting 90 (Agenda) (Minutes) PSB Dump Replacement - Strategy and Status, A. Sarrió
08.11.2012 PS Booster Upgrade Working Group Meeting 89 (Agenda) (Minutes) SMIT vs. TRIUMF magnets for Booster Inj. Line, A. Aloev
25.10.2012 PS Booster Upgrade Working Group Meeting 88 (Agenda) (Minutes)  
11.10.2012 PS Booster Upgrade Working Group Meeting 87 (Agenda) (Minutes) Timeline H- Injection, W. Weterings
04.10.2012 PS Booster Upgrade Working Group Meeting 86 (Agenda) (Minutes)  
20.09.2012 PS Booster Upgrade Working Group Meeting 85 (Agenda) (Minutes) Follow-up of the PSB dump review
13.09.2012 PS Booster Upgrade Working Group Meeting 84 (Agenda) (Minutes) MPS planning, F. Boattini
30.08.2012 PS Booster Upgrade Working Group Meeting 83 (Agenda) (Minutes) Review of the PSB Dump
16.08.2012 PS Booster Upgrade Working Group Meeting 82 (Agenda) (Minutes)  
26.07.2012 PS Booster Upgrade Working Group Meeting 81 (Agenda) (Minutes) BTV prototype at the stripping foil, A. Ravni
19.07.2012 PS Booster Upgrade Working Group Meeting 80 (Agenda) (Minutes) Integration of the Injection Region, J-M Lacroix
05.07.2012 PS Booster Upgrade Working Group Meeting 79 (Agenda) (Minutes) MPS for PSB - preliminary design and planning
21.06.2012 PS Booster Upgrade Working Group Meeting 78 (Agenda) (Minutes) Review on shorter PSB main dipole magnets
14.06.2012 PS Booster Upgrade Working Group Meeting 77 (Agenda) (Minutes) PSB dump cooling (RP recommendations, CV), PSB dump design status, Procedures for dump dismantling
31.05.2012 PS Booster Upgrade Working Group Meeting 76 (Agenda) (Minutes) LS1 work and cabling requests
24.05.2012 PS Booster Upgrade Working Group Meeting 75 (Agenda) (Minutes)  
10.05.2012 PS Booster Upgrade Working Group Meeting 74 (Agenda) (Minutes) OP priority list for BI
03.05.2012 PS Booster Upgrade Working Group Meeting 73 (Agenda) (Minutes) BT.BHZ10 Upgrade, W. Bartmann, A. Newborough (slides)
26.04.2012 PS Booster Upgrade Working Group Meeting 72 (Agenda) (Minutes) Internal H0/H- dump, M. Delonca (slides)
19.04.2012 PS Booster Upgrade Working Group Meeting 71 (Agenda) (Minutes)  
05.04.2012 PS Booster Upgrade Working Group Meeting 70 (Agenda) (Minutes) PSB magnetic cycle 900 ms, A. Blas(slides)
29.03.2012 PS Booster Upgrade Working Group Meeting 69 (Agenda) (Minutes) Update on PSB Injection with Linac4
22.03.2012 PS Booster Upgrade Working Group Meeting 68 (Agenda) (Minutes)  
15.03.2012 PS Booster Upgrade Working Group Meeting 67 (Agenda) (Minutes) Update on PSB Injection with Linac4
01.03.2012 PS Booster Upgrade Working Group Meeting 66 (Agenda) (Minutes) Sensitivity study of BLMs to beam losses, S.Damjanovic(here); Cabling strategies, J-C.Guillaume(here)
23.02.2012 PS Booster Upgrade Working Group Meeting 65 (Agenda) (Minutes) Update on PSB Injection with Linac4
16.02.2012 PS Booster Upgrade Working Group Meeting 64 (Agenda) (Minutes) RP-Cooling circuit for future PSB dump, R. Froeschl (here)
02.02.2012 PS Booster Upgrade Working Group Meeting 63 (Agenda) (Minutes) Planning for the new PSB dump, S. Mathot (here)
26.01.2012 PS Booster Upgrade Working Group Meeting 62 (Agenda) (Minutes) Update on PSB Injection with Linac4
19.01.2012 PS Booster Upgrade Working Group Meeting 61 (Agenda) (Minutes) Preliminary design of the dump, A. Sarrió Martinez (slides)
12.01.2012 PS Booster Upgrade Working Group Meeting 60 (Agenda) (Minutes) Prioritization of cabling needs, P. Bonnal (slides)
08.12.2011 PS Booster Upgrade Working Group Meeting 59 (Agenda) (Minutes)  
01.12.2011 PS Booster Upgrade Working Group Meeting 58 (Agenda) (Minutes)  
17.11.2011 PS Booster Upgrade Working Group Meeting 57 (Agenda) (Minutes) PSB dump replacement, A. Sarrió Martinez (slides)
03.11.2011 PS Booster Upgrade Working Group Meeting 56 (Agenda) (Minutes)  
20.10.2011 PS Booster Upgrade Working Group Meeting 55 (Agenda) (Minutes)  
13.10.2011 PS Booster Upgrade Working Group Meeting 54 (Agenda) (Minutes) Beam sizes for the BTM dump, W. Bartmann (slides)
06.10.2011 PS Booster Upgrade Working Group Meeting 53 (Agenda) (Minutes) Study to replace on BT.BHZ10 and on new optics on extraction line, W. Bartmann (slides)
29.09.2011 PS Booster Upgrade Working Group Meeting 52 (Agenda) (Minutes)  
15.09.2011 PS Booster Upgrade Working Group Meeting 51 (Agenda) (Minutes)  
01.09.2011 PS Booster Upgrade Working Group Meeting 50 (Agenda) (Minutes) RF renovation planning, M. Poaluzzi (slides)
18.08.2011 PS Booster Upgrade Working Group Meeting 49 (Agenda) (Minutes)  
11.08.2011 PS Booster Upgrade Working Group Meeting 48 (Agenda) (Minutes)  
21.07.2011 PS Booster Upgrade Working Group Meeting 47 (Agenda) (Minutes)  
30.06.2011 PS Booster Upgrade Working Group Meeting 46 (Agenda) (Minutes)  
23.06.2011 PS Booster Upgrade Working Group Meeting 45 (Agenda) (Minutes)  
16.06.2011 PS Booster Upgrade Working Group Meeting 44 (Agenda) (Minutes)  
09.06.2011 PS Booster Upgrade Working Group Meeting 43 (Agenda) (Minutes) Introduction to WBS, J. de Jonghe (slides)
26.05.2011 PS Booster Upgrade Working Group Meeting 42 (Agenda) (Minutes) BTY @ 2GeV, D. Voulot (slides)
19.05.2011 PS Booster Upgrade Working Group Meeting 41 (Agenda) (Minutes)  
12.05.2011 PS Booster Upgrade Working Group Meeting 40 (Agenda) (Minutes) KSW Pulse form with Linac4 injection, C. Bracco(slides); RCS Lattice Option , M. Fitterer(slides)
05.05.2011 PS Booster Upgrade Working Group Meeting 39 (Agenda) (Minutes)  
28.04.2011 PS Booster Upgrade Working Group Meeting 38 (Agenda) (Minutes)  
21.04.2011 PS Booster Upgrade Working Group Meeting 37 (Agenda) (Minutes) RCS design choices, H. Schoenauer (slides)
14.04.2011 PS Booster Upgrade Working Group Meeting 36 (Agenda) (Minutes) PS 2GeV Injection – Feasible?, W. Bartmann(slides)
07.04.2011 PS Booster Upgrade Working Group Meeting 35 (Agenda) (Minutes) Update on RCS lattice design, M.Fitterer(slides); RCS Preliminary beam transfer considerations, B. Goddard(slides)
31.03.2011 PS Booster Upgrade Working Group Meeting 34 (Agenda) (Minutes) 2 GeV protons for ISOLDE, T. Stora(slides)
24.03.2011 PS Booster Upgrade Working Group Meeting 33 (Agenda) (Minutes)  
17.03.2011 PS Booster Upgrade Working Group Meeting 32 (Agenda) (Minutes)  
10.03.2011 PS Booster Upgrade Working Group Meeting 31 (Agenda) (Minutes)  
24.02.2011 PS Booster Upgrade Working Group Meeting 30 (Agenda) (Minutes)  
17.02.2011 PS Booster Upgrade Working Group Meeting 29 (Agenda) (Minutes)  
10.02.2011 PS Booster Upgrade Working Group Meeting 28 (Agenda) (Minutes) Advanced Connection of Linac4 to PSB, W. Weterings, J. Borburgh (slides)
03.02.2011 PS Booster Upgrade Working Group Meeting 27 (Agenda) (Minutes) Upgrade of Vacuum System, E. Mahner (slides)
13.01.2011 PS Booster Upgrade Working Group Meeting 26 (Agenda) (Minutes)  
09.12.2010 L4BCC on PSB Injection (Agenda) (Minutes)  
02.12.2010 PS Booster Upgrade Working Group Meeting 25 (Agenda) (Minutes) PSB Injection Modifications, W. Weterings (slides)
01.12.2010 Workshop of the LIU Project (Agenda) (Minutes)  
18.11.2010 PS Booster Upgrade Working Group Meeting 24 (Agenda) (Minutes) Upgrade of Electrical System, S. Olek (slides)
04.11.2010 PS Booster Upgrade Working Group Meeting 23 (Agenda) (Minutes)  
21.10.2010 PS Booster Upgrade Working Group Meeting 22 (Agenda) (Minutes)  
07.10.2010 PS Booster Upgrade Working Group Meeting 21 (Agenda) (Minutes) Alternative for Booster MPS, S. Pittet (slides)
16.09.2010 PS Booster Upgrade Working Group Meeting 20 (Agenda) (Minutes) Alternative Magnetic Cycles, C. Carli (slides); Magnet Tests in SM 18, A. Newborough (slides)
02.09.2010 PS Booster Upgrade Working Group Meeting 19 (Agenda) (Minutes) Report on MD Results and Implications on PSB Upgrade, G. Rumolo (slides)
26.08.2010 PS Booster Upgrade Working Group Meeting 18 (Agenda) (Minutes)  
29.07.2010 PS Booster Upgrade Working Group Meeting 17 (Agenda) (Minutes)  
15.07.2010 PS Booster Upgrade Working Group Meeting 16 (Agenda) (Minutes) Damping Resistors on PSB Bending Magnets, A. Newborough (slides)
01.07.2010 PS Booster Upgrade Working Group Meeting 15 (Agenda) (Minutes)  
24.06.2010 PS Booster Upgrade Working Group Meeting 14 (Agenda) (Minutes) Expected Beam Loss Figures and Cures, G. Rumolo, S. Gilardoni (slides)
17.06.2010 PS Booster Upgrade Working Group Meeting 13 (Agenda) (Minutes) PS Low Energy Magnets, S. Gilardoni (slides)
10.06.2010 PS Booster Upgrade Working Group Meeting 12 (Agenda) (Minutes)  
03.06.2010 PS Booster Upgrade Working Group Meeting 11 (Agenda) (Minutes)  
12.05.2010 PS Booster Upgrade Working Group Meeting 10 (Agenda) (Minutes)  
06.05.2010 PS Booster Upgrade Working Group Meeting 9 (Agenda) (Minutes)  
29.04.2010 PS Booster Upgrade Working Group Meeting 8 (Agenda) (Minutes) Magnetic Cycle from 50 MeV to 2 GeV, A. Blas (slides)
15.04.2010 PS Booster Upgrade Working Group Meeting 7 (Agenda) (Minutes)  
08.04.2010 PS Booster Upgrade Working Group Meeting 6 (Agenda) (Minutes)  
01.04.2010 PS Booster Upgrade Working Group Meeting 5 (Agenda) (Minutes)  
25.03.2010 PS Booster Upgrade Working Group Meeting 4 (Agenda) (Minutes)  
18.03.2010 PS Booster Upgrade Working Group Meeting 3 (Agenda) (Minutes) Results on Showstopper Identification (slides)
11.03.2010 PS Booster Upgrade Working Group Meeting 2 (Agenda) (Minutes) First Status Report on Show Stoppers for PSB 2 GeV Upgrade (slides)
04.03.2010 PS Booster Upgrade Working Group Meeting 1 (Agenda) (Minutes)  

Other Meetings

Date Title Minutes
01.06.2018 Linac4-to -PSB Injection Scheme and Linac4 Feed-Forward Algorithm Minutes
24.05.2018 Discussion about the KSW/BSW/Bdl/QSTRIP Synchronisation at PSB Injection Agenda and Minutes
01.09.2017 Discussion on the Upcoming Vacuum Test for the LS2 Head and Tail Dumps (Minutes)
08.06.2017 Upgrade of PSB Cooling Station (Minutes)
31.05.2017 Follow up on Building 245 (Minutes)

-- GianPieroDiGiovanni - 20-Oct-2015

Edit | Attach | Watch | Print version | History: r427 < r426 < r425 < r424 < r423 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r427 - 2020-02-18 - GianPieroDiGiovanni
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    PSBUpgrade All webs login

This site is powered by the TWiki collaboration platform Powered by PerlWeb page setup by Thomas Hermanns