Major meeting goals and topics : PTB/PEB Information, Development and Test Plan Debriefing
Old Tasks to Follow up:
[DONE] Task Morris: to get in touch with Christina, release manager (DSA2.1) - get JRA1 Leaders in the loop
[In Progress] Task Morris : Test plan discussion with Andrea
New Tasks (high priority)
[In Progress] Task (all) : All in JRA1 (leaders/PTs) look at the EMI-1 release page to continously improve this development and test plan where necessary, updates send to Morris
Andrea - Yes (comments, etc.) - ARGUS new release in EMI not really covered by high level objectives (component improvements and new features) * Not only new development - Technical Objective "Pure Component Improvements", Components with component improvements listed there, ARGUS
Aleksandr - Technical details - PT leaders --> Area leaders covered!
Patrick - yes --> E-mails about all
John - yes - Comments to security objective (VOMS mentioned, attributes, )
Marco - not yet - will do soon
Laurence - missing in the telcon
New Tasks
[DONE] Task (all): Encourage your developers to come to the meeting and the JRA1 internal session
[DONE] Task (Morris) : Clarify with Florida that 2 reviewers are enough, remaining reviews have been cancelled (i.e. Andrew)
[DONE] Task (Morris) : learn EVO and organize EVO conferences
[DONE] Task (Andrea) : Setup EVO meeting regularly in EVO
[DONE] Task (all): Check the EMI-1 Release Hints
[In Progress] Task (all): Look at the DNA1.3.1 Overall Technical Plan, review its updates
[In Progress] Task (all) : When reviews completed, revise documents as soon as possible to get them out quickly!
[In Progress] Task (Morris, Andrea) - > test cases must be created until end of 02/2011, SA2 guidelines and unit tests should be considered
[In Progress] Task (Morris, Andre, Andrea): JRA1.7 integration testing strategy per objective to be discussed with PTs : only the plan, not its existence at 10/2010, but tests should be
[In Progress] Task (Morris, Balazs) : UNICORE (Compute) - UNICORE (Data) - (Discussion in UNICORE community & PTB)
[In Progress] Task (Morris, Balazs): Jobwrapper (PTB agenda) - Waiting for PTB outcome of discussion available 02/2011
[In Progress] Task (all) : All in JRA1 (leaders/PTs) look at the EMI-1 release page to continously improve this development and test plan where necessary, updates send to Morris
[In Progress] Task Morris : Test plan discussion with Andrea
[In Progress] Task (all): Look at the DNA1.3.1 Overall Technical Plan, review its updates
[In Progress] Task (all) : When reviews completed, revise documents as soon as possible to get them out quickly!
[In Progress] Task (Morris, Andrea) - > test cases must be created until end of 02/2011, SA2 guidelines and unit tests should be considered
[In Progress] Task (Morris, Andre, Andrea): JRA1.7 integration testing strategy per objective to be discussed with PTs : only the plan, not its existence at 10/2010, but tests should be
[In Progress] Task (Morris, Balazs) : UNICORE (Compute) - UNICORE (Data) - (Discussion in UNICORE community & PTB)
[In Progress] Task (Morris, Balazs): Jobwrapper (PTB agenda) - Waiting for PTB outcome of discussion
New Tasks
[DONE] Task (Morris) : Check with PO to remove Andrew from reviewers
[UNDONE] Task (Patrick) : Move milestone about Data Security; Patrick sends info to Florida
[UNDONE] Task (Patrick) : Contact Florida to check with Jens aspects/revised deliverable
[UNDONE] Task (John) : Discuss concrete statements and feedback with SA2 w.r.t. to the deliverable
[UNDONE] Task (Morris) : Getting severe - we need alternative reviewers although already proposed
[UNDONE] Task (Aleksandr) : Clarify update on the reviewers with POs too.
[UNDONE] Task (John) : send e-mail to Florida about milestone done (but reporting of it is mid/Nov)
[UNDONE] Task (ALL) : Collect comments about SA2 work
[UNDONE] Task (ALL) : Each components in the technical objectives add a change management tracker link (where is the change tracked)
[UNDONE] Task (Morris) : Send the link around to have a view on this SQAP
[UNDONE] Task (ALL): SQAP (at least task leaders and PT leaders) should be read to plan/work according to rules
[UNDONE] Task (ALL) : First call of ideas & comments; Objectives of the Development Plan and dive into the Testing Strategies aligned with some of the technical objectives
[UNDONE] Task (ALL) - add alpha/beta /production comments to the objectives of the development plan in the wiki page